Findings addressed by Xcel, but not Greene
in spite of PLTF warning
|
Judge’s Finding |
Xcel Memo |
PLTF Warning |
Greene Memo |
|
There are only two possible transmission line routes through |
City elected not to
adopt the other alternative route through the City—i.e., along Highway 110
and There is no alternative to
the proposed line (p. 12) On |
[T]he 110 route…is not the
only available route through the city, as the I-494 is also available…There
are many alternatives to the proposed line. (Comments on Xcel p.3 and
4), Xcel and CAI repeatedly suggested
something that either knew or should have known was not true: they repeatedly
stated the line could not be built along I494. (Comments on SFL Memo, p. 4) |
(Not addressed) |
|
In order to counter the information offered by Collier Towle, PLTF
members submitted three letters from metro area realtors to the Planning
Commission and City Council…. It was unreasonable for
City to ignore City Collier Towle's uncontroverted expert opinion, especially
in light of the fact that City selected them to prepare it |
To support its finding of
property value diminution…City relies on…three real estate agents’ anecdotal
opinion…(p.xxvii) |
One of our (uncompensated)
experts maintains the database used by CAI/Xcel’s expert. It concluded that Collier Towle misused the
database. (Comments on SFL Memo, item 8)
[The reference here is to real estate appraisal specialists, Capital
Appraisals.] |
(Not addressed) |
|
City has determined that the Project will reduce existing EMF levels
by as much as 80% |
In fact, City’s EIR Report
found the project would dramatically reduce the EMF levels. (pp. xi and 17) |
Not true. First, Xcel had disguised the fact that the
proposed second circuit would not serve the same substation as the existing
circuit. This was only learned at the |
(not addressed) |
|
The Project has been subjected to environmental review by the MEQB
and MPUC. The Minnesota Department of Health (MDH) has also reviewed it. MEQB staff conducted a review of recent developments in scientific
literature regarding EMF including the National Research Council and the
National Institute of Environmental Health Sciences reports released in
1999[8] and concluded that "the current evidence does not indicate that
the electric and magnetic fields expected from transmission lines represent a
potential for significant environmental effect." |
City is bound by these
state agencies. (p.18) The municipalities with
jurisdiction over the proposal, notably City, are otherwise bound by MEQB’s
decision on the project. |
The MPUC and MEQB conclusions
were based upon studies that are now
known to be wrong. The city is under no obligation to ignore
the scientific evidence refuting the earlier studies merely because that
suits Xcel’s convenience. As for the
MDH, the city listened carefully to its representative who testified before the
Council. It did not find the
representative’s testimony to be convincing.
The MDH has no special experience or authority regarding magnetic
fields, nor has it conducted any significant review. (Comments on Xcel memo
p. 3). The PUC and the MEQB reviewed
the SE Metro Line three years ago. You
correctly noted that neither was reviewing whether the line should be
approved. Had the MEQB approved the
EIS, it still would not have passed judgment on the line because it did chose
to not appoint itself the Responsible Government Unit (RGU). As a result, the audience for the EIS would
have been the same city councils that have reviewed the line. (Comments on
SFL Memo p.5) |
Not specifically addressed,
although the Greene memo did note the MPUC addressed the issue of shutting
down the existing line and that the MEQB suggested local communities should
deal with the issue. |
Findings
addressed by Xcel, but by neither the PLTF or Greene
|
Judge’s Finding |
Xcel Memo |
Comment |
Greene Memo |
|
||
|
The existing line does not meet Xcel's double
contingency planning requirements, |
City attorney admits that
City’s EIR Report concludes that the project…is needed to satisfy Xcel
Energy’s double Contingency Requirement |
Statement from PLTF’s
consultant, MSB Associates, says double contingency inappropriate here. |
Not addressed |
|||
|
City's zoning code provides, "[a]ny
established use or building legally existing prior to the establishment of
this Ordinance and which is therein classified as a conditional use may be
continued in like fashion and activity.
Therefore, Xcel's 75-year-old transmission line has
"automatically-received conditional use approval. |
City’s Ordinance does not
allow for denial. (p. 10) |
This does not mean the new
line benefits from the grandfathering of the old line. The key word
here is “like.” The amount of “activity” (as measured by current) would
double under the line, and the doubling of the circuits could be construed as
not continuing in like fashion. |
Not addressed |
|||
Finding addressed by only by the PLTF
|
Judge’s Finding |
Xcel Memo |
PLTF Warning |
Greene Memo |
|
Recognizing that the Gonzales report contemplated an upgrade of the
entire Red Rock to |
(not addressed) |
In this letter, CAI’s
engineer Shaffer does not defend the original conclusions, but, without
explanation, suggests that the project is still needed because it does
“reinforce the power system into the |
(not addressed) |
Findings
addressed by neither Xcel, the PLTF, or Greene
|
Judge’s Finding |
Xcel Memo |
Comment |
Greene Memo |
|
||
|
City surveyed the residents of |
not addressed |
The poll did not address
and the finding did not describe funding alternative routes. Rather,
the poll asked about working to oppose the proposal. Finding 42
reads, “The March 2000 questionnaire asked whether residents would be willing
to assume an annual financial commitment to actively work to oppose or change
Xcel’s transmission line proposal. Of the 103 respondents, 57 stated
they would be willing to make a commitment of five years; of these, 34 would
agree to an annual commitment of more than $500.” The poll said nothing
about favoring or not favoring a proposal to finance an alterative. |
not addressed |
|||
|
Virtually no one testified before any responsible
governmental body to a lack of need for the Project. |
not addressed |
PLTF President and Engineer
Dave Herridge testified at length on the issue of need |
not addressed |
|||