STATE OF
IN COURT OF
APPEALS
CASE NO.
C3-02-1409
Power Line Task Force, Inc.
Appellant
v.
Northern States Power
Company
d/b/a Xcel Energy, Inc. and
City of
Respondent
BRIEF OF APPELLANT
|
Marshall
H. Tanick (108303) 1700
Pillsbury Center South (612)
339-4295 and LAW OFFICE OF CHRISTOPHERTHOMAS
JOHNSON Christopher
Thomas Johnson (0303744) P.O.
Box 86 (612)
386-8743 ATTORNEYS FOR APPELLANT POWERLINE TASK FORCE, INC. |
BRIGGS & MORGAN, P.A. Jack
Y. Perry (209272) 2400
IDS Center (612)
334-8400 and Of Counsel Harold
J. Bagley (3906) Assistant
General Counsel Xcel
Energy (612)
251-4586 ATTORNEYS FOR RESPONDENT NORTHERN STATES POWER COMPANY d/b/a XCEL ENERGY * * * * GREEN ESPEL P.L.L.P. Clifford
M. Green (37436) William
P. Hafner (258349) (612)
373-0830 |
|
|
ATTORNEYS FOR RESPONDENT CITY OF |
B. The Sunfish Lake Proceedings
F. Subsequent Settlement and Dismissal
I.
THE TASK FORCE PROPERLY INTERVENED IN THIS
CASE
B. The Intervention Was Proper Under Rule 24
II. DISMISSAL OF THE CASE WITH PREJUDICE
VIOLATES RULE 41.01(B) AND WAS IMPROPER
B. Dismissal of the lawsuit with
prejudice was improper
C. The City had a rational basis for denying the
CUP.
1. The record reasonably reflects an absence of a
need for the project.
a.
A Required Certificate From the PUC was Lacking
b.
The Evidence About Need Was Conflicting
c. The Project
was not a non-conforming use
2. The diminution of property values constitute a rational basis to deny the CUP.
3. The adverse health risks associated with the project also form a rational basis for denying the CUP.
4. Summary of Council’s decision
I.
Was it proper to permit intervention under
Rule 24,
The
Trial Court held in the affirmative, allowing the group to intervene under Rule
24 of the Minnesota Rules of Civil Procedure.
Appellants maintain that the decision of the Trial Court was
correct. Norman v. Refsland, 383 N.W.2d 673, 678
(Minn. 1986); Costley v. Caromin House,
Inc., 313 N.W.2d 21, 28-29 (Minn. 1981); Snyder’s Drug Stores, Inc., v. Minn. State Bd. of Pharmacy, 221
N.W.2d 162, 166 (Minn. 1974); BE & K Constr. Co. v. Peterson, 464 N.W.2d 756 (Minn. Ct. App.
1991).
* *
* * *
* * *
* * * *
II. Did the Trial Court err in dismissing this lawsuit with prejudice, over the objection of the Intevenor, without providing terms or conditions that are “proper” to protect the right of Intevenor to appeal from an earlier mandamus decision entered by the Court?
The
Trial Court held in the negative, ordering that the lawsuit be dismissed with
prejudice and without providing any terms or conditions to permit the Intevenor to appeal from the earlier decision.
Appellant
maintains that the decision of the Trial Court dismissing the case with
prejudice was erroneous. Lang v. William Bros Boiler & Mfg. Co.,
85 N.W.2d 412 (
* *
* * *
* * *
* * * *
III.
Did the Trial Court err in directing the
City of
The Trial
Court ruled in the affirmative, holding that the decision by the City Council
of Sunfish Lake to deny a CUP was arbitrary, capricious, and unreasonable and
ordered the City to grant the application.
Appellant
maintains that the decision by the Trial Court was erroneous and should be
reversed. Interstate Power Co., Inc. v. Nobles County Bd. of Comm’rs,
617 N.W.2d 566 (Minn. 2000); Honn v. City of Coon
Rapids, 313 N.W.2d 409 (Minn. 1981); State
v. Larson Transfer & Storage, Inc., 246 N.W.2d 176 (Minn. 1976); Beck v. City of St. Paul, 231 N.W.2d 919
(Minn. 1975).
STATEMENT OF THE CASE
This
is an appeal from a determination by the Dakota County District Court, the
Honorable Rex Stacey, concerning an effort by Northern States Power Company
d/b/a Xcel Energy (“Xcel”) to replace a single-circuit electric power line with
a new more intensive double-circuit transmission structure running through the
City of Sunfish Lake. After its
application for a Conditional Use Permit (CUP) to replace the line was denied
by the City, Xcel sued the City seeking Mandamus directing it to grant the
application.
The
City initially opposed the lawsuit. It
was joined by the Power Line Task Force, Inc. (“Task Force”), an organization
consisting of residents effected by Xcel’s proposal, as well as two individual
homeowners, who sought to intervene in the action. The Trial Court allowed them to intervene
under Rule 24 of the Minnesota Rules of Civil Procedure.
The
Trial Court, on a motion for Partial Summary Judgment by Xcel, ordered the City
by Mandamus to issue the CUP for replacement of the power line. The Intervenors intended to appeal, but in
the meantime, Xcel and the City without involvement of the Intervenors, entered
into a Settlement Agreement. Under the
Agreement, the City granted the CUP, and the City and Xcel, without the
participation of the Intevenors, stipulated to a
proposed Court order dismissing the lawsuit with prejudice.
The
Intervenors, who were not signatories to the settlement or stipulation, opposed
dismissal of the lawsuit with prejudice.
The Court, without notice to Intervenors, signed the order requested by
the City and Xcel to dismiss the lawsuit with prejudice. Rule 41.01(b) Minn. R. Civ.
P. states that a lawsuit may not be dismissed with prejudice unless all parties
agree or the Court does so upon terms and conditions that are “proper.” After signing its Order, it conducted a
hearing at which Intervenors requested that the matter not be dismissed with
prejudice without protecting their right to appeal from the prior Mandamus
ruling.
The
Trial Court adhered to its prior ruling and ordered the lawsuit dismissed with
prejudice without any other terms or conditions. Judgment was then entered dismissing the
lawsuit with prejudice.
The
Task Force brought two related appeals.
The present appeal challenges: dismissal of the lawsuit with prejudice
without “proper” terms to protect the rights of the Intervenor. A separate appeal, C0-02-1285, contested the
Mandamus ruling of the Trial Court. A
Panel of this Court, on
STATEMENT OF THE FACTS
This
case concerns the attempted replacement by Xcel of an existing single circuit
power line with a new double-circuit structure bearing a different, more
intensive power line running through the community of
In
the late 1990’s, Xcel announced a project seeking to build a new double-circuit
of 115 kV transmission line covering a distance of 14.76 miles from the Red
Rock Substation in Newport to the Wilson Substation in Bloomington. App. p.15 (Finding 9), passing within 50 feet
of about 208 housing units, including apartments, including several homes in
The
existing line, supported by wooden H-frame structures ranging from 51 – 85 feet
high, is part of Xcel’s transmission grid delivering electric power to
customers throughout the Twin Cities metropolitan area. App. p.17 (Findings 10-11). Xcel sought to replace that line with steel
structures supporting double-circuit lines ranging from 80-110 feet high. App. p.17 (Finding 12). In addition to the greater height, the
proposed double circuit would have concrete foundations drilled into the ground
at a depth in excess of 30 ft, in lieu of the current wooden poles that are
embedded without permanent foundations.
The
Minnesota Public Utilities Commission (“PUC”) earlier had declined a request by
a group of citizens to remove the existing single-circuit power line. See In the matter of the Complaint regarding the safety of Northern States
Power Company’s transmission lines in the Southeast Metro Area, Docket No.
E-002/C-99-902, 2000 WL 772434 (
The
Minnesota Environmental Quality Board (“MEQB”) also declined to require the
submission of an Environmental Impact Statement in conjunction with the
proposed project. App. p.8. The MEQB could have declared itself the
“Responsible Government Unit” and passed upon the merits of Xcel’s application,
but chose not to do so, nor did it reach a judgment on whether a Statement was
needed. Stating that it was not the
“responsible governmental authority to make that determination,” the agency
agreed with the PUC that the project is “subject to local control, including
Conditional Use Permits.”
Xcel
then sought approval from the various communities through which the replacement
line would run, including
B.
The
Although
the existing line is “grandfathered” as a non-conforming use, the proposed
double circuit replacement requires a CUP and site approval under the City’s
Zoning Code, City Code § 1224.05. The
criteria for granting or denying the CUP include the protection of the public
health, safety, and welfare, the health effects, impact on surrounding
properties and need for the project.
City Code, §§ 1204 and 1224.
The
City has a multi-step process to replace or reconstruct a transmission
line. First, a CUP has to be obtained
for the project as a whole and its route, if approved, the site and building
plan approval must be obtained. City
Code § 1224.05. In addition to seeking a
CUP, Xcel also sought a minor variance from the City’s requirement that poles
be 60 ft from houses and conductors be at least 37.5 ft from homes, although
the 50-foot width of the easement would remain unchanged. App. p.17 (Finding 16).
Under
the Sunfish Lake Zoning Code, when an application is made for a CUP for a
transmission line, the City Counsel is to consider other potential routes in
addition to that proposed by the applicant.
City Code § 1224.05 (F) and (G).
Scrutiny of the project consists of public hearings before the Planning
Commission, which makes a recommendation of the City Council for approval or
denial. Following public hearings, the
council makes a decision. If the
application is approved, the council next addresses a proposal for site
specific construction details, known as the site and building plan stage; if
the CUP is not granted, no further action is taken.
Three
of the effected communities, including
Significant
health issues pertained to the replacement power line upon those living
nearby. Power frequency magnetic fields
arise from electric currents. They are
part of the electromagnetic field (EMF) associated with every power line. The intensity of a magnetic field is a
function of the amperage going through the line. The greater the current transmitted, the
greater is the magnetic field intensity.
The intensity of a magnetic field varies with the distance from the
source. App. p.19 (Finding 23.)
The
proposed line would carry a great deal of current, up to 1600 amps in each of
its two circuits. App. pp.16,20 (Findings
9, 24-25). It would pass within 30 feet
of houses, much closer than Xcel’s own practice for new lines according to
Xcel’s own estimates, and would expose the residents of adjacent homes to
magnetic fields more than 40 times more intense than the average residential
fields in the United States.
Health
hazards posed by power lines have been of concern since 1971. [2] The issue is not one
of “junk” science. It has been treated
seriously by the established scientific community, physicians, and national and
international health organizations. The
adverse health effects from exposure to EMF include increased likelihood of
child leukemia, ameotrophic lateral sclerosis (ALS or
Lou Gehrig’s Disease), neurological disorders, breast
cancer, and miscarriages, among other afflictions, especially among those
already susceptible to those diseases.
App. pp.25-26 (Findings 55 – 60).
Debate
existed for many years within the scientific community regarding the
relationship between EMF and those diseases.
There were inconsistencies in the epidemiological research: some studies found a linkage and others did
not. But in 2000, in three independent
studies, scientists reexamined earlier investigations and concluded that a link
exists between EMF and a heightened risk of contracting serious diseases. App.
p.28 (Finding 70). As a result, credible
and strong scientific data shows that exposure to heightened EMF is
epidemiologically linked with an enhanced risk of contracting serious disease,
a view shared by many officials and leading government authorities, including
some who have modified their earlier doubts regarding the existence of this
linkage. [3]
The
double-circuit line proposed by Xcel initially would reduce EMF in comparison
to the existing single-circuit line. App.
p.22 (Finding 34). But opponents of
Xcel’s plan, supported by independent experts, submitted substantial
information that the new power line would, based upon future demand, result in
an increase in amps and EMF that could endanger the health of those living near
the site. App. p.25 (Findings 54 –
55). Some of this testimony was
furnished by Dr. Martin Blank, a Microbiologist and Professor of Physiology at
Their
views, along with voluminous supporting documents, were provided to the
Steering Committee and were part of the record used by the Sunfish Lake City
Council in evaluating Xcel’s request for a CUP.
App. pp.35-44. Documentation also
was submitted from MSB, an independent engineering consulting firm, casting
doubt upon Xcel’s projections concerning the intensity of power line usage and
resulting EMF. App. p.38. Four practicing physicians (a surgeon,
OB/GYN, radiologist, and general practitioner) also testified about potential
health effects resulting from increased future exposure to EMF from the
proposed new line.
Xcel
submitted testimony of one health-related consultant and a mid-level official
from the Minnesota Department of Public Health.
In contrast, Jan Malcolm, the Commissioner of the State Department of
Public Health, wrote that “[f]rom a public health
standpoint, I am concerned about the level of magnetic field exposure (EMF) to
which certain residents are now and will continue to be subject,” noting that
Xcel’s project was anticipated to generate much greater exposure levels than
those in the MEQB studies.
The
Mayoral Steering Committee did not adopt any report nor issue conclusions or
recommendations of its own. The Sunfish
Lake Planning Commission held three lengthy hearings in December, 2001 and
January, 2002, consuming about ten hours, and received more than 100 documents,
comprising in excess of 2,000 pages, along with live testimony, forming the
voluminous administrative record in this case.
App. p.43. During the proceeding,
Xcel orally stated, without supporting documentation, that it would defer its
14-plus mile project and limit the proposal to a 6.36 segment running from the
Red Rock Substation in
The
City considered three available options: an above-ground double circuit 115 kV
transmission line; a below-ground double circuit 115 kV transmission line; a
below-ground double circuit transmission line; or denial of the project. App. p.18 (Finding 17). Xcel maintained that the project was
necessary and that a below-ground line would be economically unfeasible,
costing some $6.5 million, compared to $500,000 for an above-ground structure. App. p.23 (Findings 36-37).
Opposition
to the project focused on several issues: diminution of the value of adjoining
properties, adverse health effects due to increased exposure to EMF, and lack
of need for the project. App. p.18
(Finding 18).
The
City was guided through the process by its City attorney, who emphasized the
importance of basing any action on facts in the record and drafted alternative
proposed findings of fact, one supporting approval of the CUP and the other
containing supporting denial, which were made available to Xcel members of
public, including opponents of the project, who offered extensive comments to
the alternate versions, which were modified as the process progressed. On
The
Findings included a determination that the project “will cause a reduction in
the market value” of homes in the vicinity of the power line. App. p.19 (Finding 22). In evaluating health concerns, the Council
noted that several residents near the power line have “health problems” that
may be aggravated by EMF exposure, App. pp.25-26 (Finding 58), that EMF
exposure will increase over time, as demand for power rises and the increase
will “have adverse health effects,” including a greater likelihood of child
leukemia, ameotrophic lateral sclerosis (Lou Gehrig’s Disease), neurological disorders, breast cancer
and miscarriages, among other matters, especially among those already
susceptible to those afflictions. App.
p.26 (Findings 59-60). The Council also
determined that it was not reasonable to permit the “unjustified [health] risks
. . . of constant and cumulative exposure to EMF,” that would result from the
project. App. p.26 (Findings
62-63). The Council also found that Xcel
had not “shown a demonstrated need” for the project based upon the lack of any
certificate need from the PUC or determination from that agency that a Certificate
of Need was not required. App. p.30
(Findings 86, 89).
The
City made supporting Conclusions that the project “will cause a reduction of
the market value” of homes in the area, App. p.33 (Conclusion F), that
“credible” evidence exists of “adverse” health effects stemming from the
project, App. p.33, (Conclusions D and E), and that there was no showing of a
“need for the project” at the present time.
App. p.34 (Conclusion H).
Coupled
with its Findings and Conclusions, the Council identified a voluminous record
of 109 items of testimony, reports, and other materials that constituted the
record and support its determination, including appraisal materials concerning
real estate values; numerous reports about adverse health effects from EMF,
including testimony from two experts, Dr. Blank and Dr. Havas,
and four local physicians, and numerous other data gathered during the process
as well as from hearings from other nearby cities regarding efforts by Xcel to
replace its power line in those communities, too. App. pp.35-44.
Xcel
sued the City on
Xcel
brought a Motion for Partial Summary Judgment seeking Mandamus for issuance of
a CUP. App. pp.81-82. The City made a cross-motion for summary
judgment. App. p.96. The Task Force and two individual residents
timely sought intervention as Defendants.
App. pp.97-98. At a hearing on
the cross-motions for Summary Judgment, the Court permitted them to intervene,
over objection of Xcel. App. ____. Although granted the right to intervene, the
Task Force was not allowed by the Court to make any argumentation or submit a
brief at the hearing on the Motions.
App. p.102 (Trial Court Memorandum, p.4).
On
In its
ruling, the Court determined that the City’s denial of a CUP was arbitrary,
capricious, and unreasonable. Paying
homage to the “very fine efforts” of City officials, App. p.101 (Trial Court
Memorandum, p.3), the Court reached the “inescapable conclusion” that the
denial of the CUP was “unauthorized, unreasonable, arbitrary and
capricious.” Addressing Xcel’s motion
for Summary Judgment, the Court declared that the “underlying facts are not in
dispute.”
The Court
also determined that Xcel had established need for the replacement line circuit
and that it did not need a Certificate of Need from the PUC nor a determination
by the Commission waiving a certificate since the statutory requirement for a
Certificate of Need, pursuant to Minn. Stat. §216B.242 subd.6, only applies to
projects undertaken on or after August 1, 2001 and that Xcel had initially
sought the permit prior to that date, which rendered the statute
inapplicable.
The Court
concluded that denial of the CUP was unreasonable because the City really
wanted “removal of the [existing] line altogether.”
F.
Subsequent
Settlement and Dismissal
The Task Force,
as Intervenor, planned to appeal.[5] The City and Xcel then began discussions to
resolve a case through issuance of a CUP.
The Task Force objected, urging that the Mandamus order be appealed. The Council indicated it would appeal if the
Task Force would post a bond of $135,000 to cover the City’s legal
expenses. App. pp.127-129. The Task Force agreed and arranged for a
letter of credit. App. p.130. The City recanted and, rather than appealing,
on July 2, 2002, by a vote of 4-1, flip-flopped and entered into a settlement
with Xcel July 2, 2002, which was explicitly predicated upon the Mandamus
ruling of the Trial Court. App.
pp.130,139.
In the
settlement, the City agreed to furnish a CUP in exchange for minor
consideration by Xcel, and the parties further agreed to stipulate to dismissal
of the lawsuit with prejudice.[6] The Task Force, which was not included in
discussions or a signatory to the arrangement, opposed the settlement because
it believed that the Mandamus ruling that predicated the settlement was
erroneous and should be appealed.
Xcel and
the City presented the stipulation to the Trial Court, which entered an Order
on
The Task
Force then brought this appeal, claiming that the Trial Court erred in dismissing
the case with prejudice without providing “proper” protection of its rights to
appeal the Mandamus decision. The Task
Force maintains that the Trial Court erred in not conditioning dismissal on its
right to appeal the prior Mandamus decision, which it claims was erroneous and
should be reversed.
The Task
Force also brought a separate, related appeal challenging the Mandamus
decision. Case No. CO-02-1285. A Special Term Panel dismissed that appeal
but passed no opinion on “whether the May 31 [mandamus] order should be
reviewed in the context of [this] appeal.”
App. pp.207-208.
SUMMARY OF ARGUMENT
The
Task Force was properly allowed to intervene in this case because it satisfied
all four conditions for intervention under Rule 24, Minn. R. Civ. P. In light of
the liberal approach to intervention, the Trial Court properly allowed the Task
Force to participate as a party defendant.
But
the Trial Court erred in dismissing the lawsuit with prejudice over the
objection of the Task Force. Under Rule
41.01, a lawsuit may be dismissed with prejudice if all of the parties agree to
that disposition. Absent such agreement,
Rule 41.01(b) requires that any dismissal be conditioned upon terms that are
“proper.” In this case, it would have
been “proper” to condition any dismissal upon the express right of the
Intervenor to appeal the Mandamus decision, which formed the expressed
predicate for the subsequent settlement between Xcel and the City. Alternatively, the Trial Court could have
stayed its mandamus order to enable the Task Force to have sufficient time and
opportunity to appeal that determination prior to the issuance of a CUP. The failure of the Trial Court to condition
to dismissal upon terms that protect the rights of the Task Force was erroneous
and should be reversed.
On
the merits, the decision by the Trial Court overturning the denial of the CUP
by the City on grounds that it was arbitrary, capricious, and unreasonable was
erroneous. Under the narrow standard for
review of municipal land-use planning decisions, the Court should have given
deference to the City Council’s determination, which was based upon a
compelling and substantial record. The
voluminous data before the Council adequately reflected grounds to deny the CUP
based upon the adverse impact upon property values, deleterious effects upon
health, and lack of need for the project.
The
Trial Court essentially placed itself in the position of decision-maker and,
rather than deferential review, weighed the evidence presented to the City Council
and substituted its judgment for that of the elected officials. This determination was improper because the
City’s denial of the CUP was factually based upon the evidence before it. The Trial Court erred in substituting its
judgment for that of the Council, and its determination should be reversed.
ARGUMENT
I.
THE TASK FORCE PROPERLY INTERVENED IN THIS CASE
Intervention
under Rule 24, Minn. R. Civ. P. is to be liberally
construed.
B. The Intervention Was Proper Under Rule 24
The
Trial Court’s determination is correct and should be affirmed. A party is entitled to intervene under Rule
24 if it satisfies four requirements: (1) makes a timely request; (2) has an
interest relating to the issue in the lawsuit; (3) the disposition of the
lawsuit may, as a practical matter, prevent or impair the intervenor’s
ability to protect its interest; and (4) the existing parties do not adequately
represent the interests of the intervenor.
Rule 24.01, Minn. R. Civ. P; see also Minneapolis Star & Tribune Co. v.
Schumacher, 392 N.W.2d 197, 207 (Minn. 1986).
The
Task Force met all of these criteria. It
filed an Answer, which was later amended.
App. pp.149-160, and timely moved the Trial Court to intervene, as
permitted at the Summary Judgment hearing.
App. p.99.
The
Task Force clearly has an interest in the CUP application, which is the subject
of litigation. Its members all live in
the City of Sunfish Lake; the value of their homes will be diminished, and
those living near the site are likely to suffer the adverse health effects
found by the City Council to be a probable by-product of the project. Thus, they have a cognizable interest in the
subject of this lawsuit. Jerome Faribo
Farms, Inc. v. County of Dodge, 464
N.W.2d 568 (Minn. Ct. App. 1990), review denied; Mille Lacs Band of Chippewa Indians v. State,
989 F.2d 994 (8th Cir. 1993); Planned
Parenthood of Minn., Inc. v. Citizens for Cmty.
Action, et al., 558 F.2d 861, 870 (8th Cir. 1977).
The
Task Force would be disadvantaged if not allowed to intervene. The subsequent settlement efforts by the City
and Xcel demonstrate that the interest of the Task Force will be affected by
the outcome of the case and they would be prevented or impaired from exercising
their rights. The interest of the Task
Force were not adequately protected by the City, as is reflected in the City’s
posture in this litigation after the Trial Court’s issuance of the Mandamus
order. It was reluctant to appeal unless
the Task Force, comprised of many citizens in the community, agreed to underwrite
the cost of the appeal. App. pp.127-129. When the Task Force agreed to do so, the City
nonetheless refused to appeal. App.
p.130. It then entered into a settlement
agreement, without involvement or participation by the Task Force, which sought
to decimate the rights of the Task Force and now takes a position directly
opposed to the Task Force. There could
not be greater adversity between a municipality and some of its citizens than
reflected in this case.
The
presence of a government body in a lawsuit occasionally precludes intervention
by its constituents, E.g., Curry
v. Regents of Univ. of Minn.,
167 F.3d 420 (8th Cir. 1999); Mausolf v. Babbitt, 85 F.3d 1295 (8th Cir.
1996). But when the interests of the
citizens are diametrically opposed to those of the governing body, as here,
intervention is permissible and proper. Jerome Faribo
Farms, Inc. 464 N.W.2d at 570-571.
The stark difference between the City Council, which wants to issue the
CUP, and the Task Force, which opposes it, warrant intervention so that the rights
of the Task Force and its members can be exercised. The Trial Court correctly allowed the Task
Force to intervene, and its determination on that issue should be affirmed.
II.
DISMISSAL OF THE CASE WITH PREJUDICE VIOLATES RULE 41.01(B) AND WAS IMPROPER.
Rule
41.01 proscribes dismissal of a lawsuit with prejudice unless agreed to by all
the parties or, under 41.01(b), upon such terms as the Court deems
“proper.” Dismissal of this lawsuit with
prejudice, over objection of the Intervenor, is reviewed under the abuse of
discretion standard. Metro. Fed. Bank of
B.
Dismissal of the lawsuit with prejudice was improper.
The
Trial Court erred in dismissing the lawsuit with prejudice. The ostensible purpose of the dismissal was
to prevent the Task Force, as an Intervenor, from challenging the Mandamus
decision directing the City to furnish a CUP, which formed the explicit basis
for the subsequent settlement between Xcel and the City. App. p.167 (Transcript, lines 14-25).
But
Rule 41.01(b) proscribes wielding dismissal in such a blunt fashion to wipe out
the right of appeal of a non-consenting litigant. The purpose of the rule is to prevent
connivance of parties in litigation, as occurred here, to restrict another
party from challenging the determinations of the Trial Court.
As an
Intervenor, the Task Force has the right to participate in litigation as a
co-equal. Lang v. William Bros Boiler & Mfg. Co., 85 N.W.2d 412, 418 (
Cases
in which dismissal with prejudice has barred a party from proceeding in an
earlier phase of a case are distinguishable.
In Sammons v. Pike, 117 N.W.
244 (
In
the present case, the issue is not whether Xcel and the City can stipulate and
reach a settlement, but the propriety of the terms of any such dismissal in
order to protect the rights of the Intervenor Task Force, a co-party defendant
in the litigation and a non-signatory to the settlement. Because the Task Force was a party in the
litigation, its rights cannot be dissipated by the unilateral actions of the
other parties in an effort to avoid an appeal of the Mandamus ruling.
The
Trial Court disregarded these requirements in running rough-shod over the
rights of the Intervenor. Ordinarily,
this review Court would, in reviewing the Mandamus ruling, require Xcel to show
that the City Council’s denial of its CUP was arbitrary, unreasonable or
capricious. Interstate Power Co.,
Inc. v. Nobles,
Thus,
the dismissal with prejudice could reverse the evidentiary standard, forcing
the Task Force to show that the City’s issuance of the CUP following the Mandamus
order was unreasonable. But the real
issue in this case is whether the Trial Court erred in deciding that the City’s
initial denial of the CUP was arbitrary, capricious or unreasonable. Interstate
Power Co., supra; Honn, supra.
It also is troubling that the Trial Court,
adopted and signed verbatim the dismissal documentation submitted by Xcel and
the City, even while the Task Force, a party to the lawsuit, was disallowed
participation in the process until after the dismissal was a fait
accompli. The Trial Court
adopted the stipulation submitted by Xcel and the City and signed it a week
before it allowed the Task Force to be heard on the issue. App. p.199.
This
procedure runs afoul of Due Process requirements of notice and a meaningful
opportunity to be heard.[10] The Supreme Court
recently reaffirmed its condemnation of this conduct, lamenting that “the
practice of the verbatim adoption of a party’s findings and conclusions is
hardly commendable.” Pederson v. State, 649 N.W.2d 161 (
The Court
below should have provided “proper” terms for dismissal of the lawsuit in order
to assure the right of the Task Force to appeal. This could have been done by directing the
entry of judgment on the Mandamus order to permit an appeal from that determination. See Ullrich v.
In
sum, the Trial Court erred in disposing of this lawsuit by dismissing it with
prejudice, over the objection of the Intervenor Task Force. Consistent with the requirement of Rule
41.01(b) that any such dismissal be conditioned upon “proper” terms, the Trial
Court should have directed the entry of judgment in the Mandamus ruling and
stayed dismissal pending this appeal so as to give this Court the opportunity
to consider the merits of the Mandamus ruling overturning the City’s denial of
the CUP. Since construction has not
begun on the project, it is not too late for the Court to reverse the dismissal
with prejudice and reverse the Mandamus ruling.
This would negate the basis of the subsequent settlement and issuance of
the CUP and allow recision of the CUP. State ex rel.
Howard v.
III.
THE TRIAL COURT ERRED IN HOLDING THAT DENIAL OF THE CUP WAS
UNREASONABLE AND ORDERING THE CITY TO GRANT THE APPLICATION.
The
Task Force, is harmed by the dismissal because it has a meritorious claim that
the Trial Court erred in its order of Mandamus overturning denial of the CUP
and directing the City to grant Xcel’s application. Because the Trial Court issued Mandamus on a
motion for Summary Judgment, the standard of review is 1) whether any genuine
issues of material fact exist, and 2) whether the District Court erred in
applying the law. Rule 56.01,
The
legal standard for reviewing denial of an application for a CUP is whether the
denial was arbitrary, capricious and unreasonable. Honn, 313 N.W.2d at
413; Trisko v. City of
Review
of a denial of a CUP is limited to “the legal sufficiency and the factual basis
for those reasons.” Trisko, 566 N.W.2d at 349.
An applicant like Xcel that is denied a CUP must show that “the reasons
stated by the council for the denial of the permit are either without factual
support in the record or are legally insufficient.” Hubbard
Broad., Inc. v. City of
Therefore,
the standard for this Court in reviewing the decision of the Trial Court is
whether there are any genuine issues of material of fact in dispute regarding
the reasonableness of the City’s action denying the CUP. If so, the determination of the Trial Court
must be reversed and Summary Judgment entered upholding the City’s denial.
Under
The
statutory scheme changed on
The
regulatory role of the MEQB also was expanded after
B.
The City had a rational basis for denying the CUP.
The
Sunfish Lake City Council based its denial of the CUP on several grounds: the
absence of any demonstrated need for the project; the diminution of property
values in the community if the
project were approved; and potential adverse health risks of the project
stemming from increased exposure to EMF.
App. p.33. This determination was
based upon a voluminous record compiled during extensive public hearings by
three bodies: the Mayors Steering Committee, the Planning Commission, and the
Council itself.
The
Council’s determination in February to deny the CUP, by a 4-1 vote, was
rationally based upon the record before it.
The Trial Court erred in re-evaluating the evidence before the City,
weighing the pros and cons, and reaching a conclusion that differed from that
of the lawmakers who are specifically vested with that duty. While some of the issues may be reasonably
debatable, the Trial Court mistakenly substituted its own judgment for that of
the Council, departing from the principle that “the duty of the judiciary [is]
to exercise restraint and accord appropriate deference to [municipal]
authorities in the performance of their duties.” White
Bear Docking v. City of White Bear Lake, 324 N.W.2d 174, 176 (
Because
of this high standard of deference, Trial Courts rarely overturn land use
decisions by municipalities, especially when a compelling, conclusive record
has been accumulated in the process, as in
The
Trial Court began its analysis from a defective premise and, not surprisingly,
ended up with a defective result. The
flaw was its view that “[t]he
underlying facts are not in dispute.”
App. p.105. This is the standard
for Summary Judgment, but was not remotely satisfied in this case. In fact, the entire municipal proceeding,
ranging from the Mayors Steering Committee to the final 4-1 vote by the City Council
denying the CUP, was replete with disputes regarding many matters, including:
§
The length of the
project, whether the 14-plus mile line, as originally proposed or the lesser
6.36 segment as Xcel sought to revise;
§
Whether there is a need
for the project, in whole or in part, as Xcel claimed, or there was no need;
§
The sufficiency of the
existing 50-foot easement for the project;
§
The effect of the
replacement line on present values, which Xcel claimed was slight and opponents
claimed was appreciable;
§
The amount and extent of
exposure to EMF resulting from the project now and in the future, which Xcel
claimed would be reduced and opponents asserted would increase as electricity
demand rises in the future;
§
The impact of the
exposure to EMF on the health of nearby residents, which Xcel claims lacks
causal connection and the citizenry maintain is dangerous then, especially
those with existing susceptibilities.
These
matters were all the subject of heated controversy during the proceedings. There was evidence presented by Xcel, as
proponent of the project, and by others in opposition on all of these contested
issues. The City Council chose to accept
some of the views advanced by both sides in
reaching its conclusion.
The
issue here is whether the City had any reasonable basis to deny the CUP.[12] That question must
be viewed through the prism of the Summary Judgment standard, which requires
that all disputed facts be regarded in the light most favorable to the
non-moving party.
In
this case, the record reflects many factual disputes. It also contains ample evidence upon which
the City could, and did, reasonably decide to deny the CUP. Any of the reasons relied upon by the City
was sufficient; all of them are overwhelming.
1.
The record reasonably reflects an absence
of a need for the project.
a.
A Required Certificate From the PUC was Lacking
As a
threshold matter, the Council’s decision must be upheld because it rationally
determined that Xcel failed to demonstrate need for the project, a
pre-requisite for granting a CUP under the City’s Zoning Code. City Code §§1204, 1224.
One
reason the CUP was denied was because of Xcel’s failure to obtain a Certificate
of Need from the PUC, as required by Minn. Stat. § 216B.243 subd.2 (2002
Supp.) The statute dictates that a
Certificate of Need from the PUC be issued to authorities before any “large
energy facility,” as defined, is “sited or constructed.” Minn. Stat. § 216B.243 subd.2. The facility for which the Certificate is
required is defined, as of August 1, 2001, to be a transmission line if 1) the
capacity of the line exceeds 100 kV, as does the Xcel project, and 2) is
greater than 10 miles in length, as was Xcel’s proposal. Minn. Stat. § 216B.242 subd.2 (2002
Supp.)
It is
undisputed that Xcel did not obtain a Certificate of Need from the PUC on or
after
The
Trial Court erred as a matter of law in overturning the City’s determination. It mistakenly reasoned that the Certificate
from the PUC was not needed under Minn. Stat. § 216B.2421 subd.6 (Supp. 2001)
because Xcel applied for approval for a new power line in nearby communities, other
than
The
Trial Court was mistaken for several reasons.
First, it cites a non-existent statute; there is no § 216B.2421
subd.6. The Court may have meant §
216B.2425, which refers to a different matter: reports of ongoing projects to the
PUC. But that statute does not exempt
facilities from PUC approval or certification under §216B.243 subd.2.
Xcel
applied on
The
Court below also erroneously stated that the City was wrong in requiring any
PUC Certificate be obtained before the CUP was approved. The Trial Court reasoned that because, a
Certificate could be obtained before construction began, the City could have
made obtaining PUC approval a condition of the PUC, rather than a reason for
denial. App. pp.124-125.
This
rationale is flawed. It interferes with
the discretion accorded municipal officials in land use decisions and
misconstrues the Certificate requirement.
The statute requires a Certificate of Need before “applying for a site
or route permit” from the MEQB or “construction of the facility.” Minn. Stat. § 216B.243 subd.4 (Supp.
2002). Thus, a “large energy facility”
project, like the one proposed by Xcel, must obtain a permit from the PUC
before siting a project, which precedes construction. The phrase “or” refers to the need to obtain
certification at the beginning of a project, not mid-way through it or the
end. Allowing Xcel to obtain a CUP
without the necessary Certificate of Need would distort the process, permitting
a lengthy and costly CUP process within a municipality that would become moot
if construction is not subsequently approved by the PUC. The blending of local authority and PUC
approval, as contemplated by the post-August 1, 2001 statutory scheme, is
accomplished by requiring the Certificate of Need from the PUC to be obtained
as a pre-condition for the granting by a municipality of a CUP, not to be
tacked on as a condition subsequent to a CUP.
The
statutory interpretation by the Trial Court was based upon its mistaken view
that
The
unilateral announcement by Xcel of its intent to change the project, from the
original 14-plus miles to a 6.63 segment during the CUP process, does not
dispense with the requirement for a Certificate of Need from the PUC. Xcel never submitted a revised application
for the shorter route to
Xcel’s
basis for the project was the claimed need for electric power over a 14-plus
mile span. App. p.30 (Finding 85). But in light of reduced demand forecasts,
Xcel sought to disavow earlier projections and indicated that it intended to
build only a 6.33 mile segment for the first stage, a proposal that the City
Council correctly regarded as “disjointed, conflicting, and unpersuasive.” App. p.30 (Finding 89). Xcel never submitted any revised data
reflective of the need for this lesser project.
Thus, the record reflected that Xcel believed it needed the 14-plus mile
project, based on outdated forecasts, and furnished no data supporting the need
for a lesser 6.33 mile segment.
Xcel
is bound by its repeated representations in its application to the City, App.
pp.9-10, as well in prior representation to the MEQB, that it contemplated a
14-plus mile project. App. p.16 (Finding
9). This length for a line in excess of
115kV invokes the Certificate of Need from the PUC under Minn. Stat. § 216B.243
subd.2 (2002 Supp). Because Xcel never
formally revised the project nor submitted any revised materials in its CUP
application, the only matter before the Council was the 14-plus mile project,
not a segmented or serial project of lesser length.
The
statutory requirement of a Certificate of Need is intended to assure that
utilities do not cavalierly circumvent PUC approval. See No Power Line, Inc. v.
b.
The Evidence About Need
Was Conflicting
The
Trial Court also erred in reasoning that there was no evidence substantiating
the lack of need for the project. The
Trial Court mistakenly placed the burden on the City to prove lack of need,
whereas the City Code imposes the duty to establish need upon the
applicant. City Code, § 1224.05.
The
Trial Court erroneously stated that “[v]irtually no
one testified . . . to a lack of need for the Project.” App. p.117.
In fact, there was abundant testimony questioning whether the project
was necessary, including testimony before both the Planning Commission and the
City Council by the Task Force that the project was not needed. This evidence was complemented by voluminous
documentation reflecting the lack of need for the project. App. p.30 (Finding 89).
The
Trial Court based its view that the project was needed solely on Xcel’s
exhortation that it was. App.
p.117. It reasoned that because Xcel
made a “business judgment” that the project was needed, the City Council must
abide by that decision.
But
the law does not require that municipal authorities slavishly acquiesce to the
business decisions of land use applicants.
If it did, as the Trial Court suggests, there would be no need for
municipalities (or the PUC or MEQB) to exercise their quasi-judicial discretion
in passing upon land use applications.
The legal authorities dispel the Trial Court’s supposition that once a
business determines the need for a project, municipal approval must occur. E.g., SuperAmerica Group, Inc. v. City of Little Canada, 539 N.W.2d 264 (Minn. Ct.
App. 1995) (rezoning not required even though site could support the proposed
use and project would not exacerbate traffic conditions); Sun Oil Co. v. Vill. of
Since
the record reasonably supported the City’s finding that the need for the
project “has not been shown,” App. p.30 (Finding 89), the Trial Court was
obligated to sustain the Council’s denial on this ground alone.
c.
The Project was not a
non-conforming use
The Trial
Court also erroneously assumed that the City had no choice but to approve
Xcel’s application because it constituted a non-conforming use, antedating the
enactment of the City Zoning Code. App.
pp.115-116. Citing the City Zoning Code,
§ 1202.06, the Trial Court stated that a pre-existing use that is “continued in
like fashion and activity” must be automatically approved.
But this
provision deals only with continuity of a non-conforming use, or
“grandfathering” of a pre-existing activity, that was lawful before enactment
of the Zoning Code. It is inapplicable
because Xcel proposes to expand the pre-existing use considerably with new,
higher, and different structures and circuits of greater intensity. The Xcel proposal does not constitute an
extension of a “like” use since the proposed new “activity” constitutes a
substantial enlargement of the pre-existing use. County of Freeborn v. Claussen, 203 N.W.2d 323
(Minn. 1972) (construction of building to house equipment that had previously
been stored in the open was an expansion of a pre-existing use); SLS
Partnership v. City of Apple Valley, 496 N.W.2d 429 (Minn. Ct. App.
1993), review granted, affirmed in
part, reversed in part, 511 N.W.2d 738 (expansion in size of mobile home on
pre-existing pad in mobile home park was an enlargement of the pre-existing
Use); County of Lake v. Courtney, 451 N.W.2d 338 (Minn. Ct. App. 1990),
(removal of cabin walls and roof and building new structure on existing
foundation with roof line six feet higher than prior line was expansion of
use).
The
Zoning Code proscribes a non-conforming use from being “enlarged or
reconstructed,” City Code § 1215.02A.
The replacement power line proposed by Xcel exceeds permissible “normal
maintenance” or “incidental alterations” allowable under § 1215.02B of the
Code. See Aegerter v. City of
The
Court also presumed that, because the proposal was a non-conforming use, the
City was obliged to approval of it, and the only issue was which alternative
route was to be selected. App.
p.117. The Court’s conclusion that the
City was not entitled “to deny the line altogether” is erroneous.
The
City Code expressly provides that application may be approved or denied. City Code § 1274.05 (F) and (G). The second step of the CUP process contains a
“no build” alternative, as well as another alternative which places the line
underground.
Thus,
the record amply reflects that the Council could approve or deny the CUP, or
approve it with a different route than that sought by Xcel. The Trial Court’s conclusion that the City
had no choice but to “automatically” approve the project was erroneous as a
matter of law. The City had the
authority to deny the application and rationally did so. Because Xcel failed to establish need for the
project, the City’s decision must be upheld and the determination of the Trial
Court reversed.
2.
The
diminution of property values constitute a rational basis to deny the CUP.
In
addition to the absence of need, abundant evidence was presented to the Council
reflecting that the replacement double-circuit transmission line would have an
adverse impact on property values in the community.
The
City Council found that there would be an adverse impact upon property values
if the CUP were granted. App. p.19
(Findings 19-22). It based its
determination on a report that showed potential reduction of sales prices for
single family homes caused by proximity to transmission lines ranging from 4%
to 7% in the
While
the Council did not determine the precise amount of diminution of property
values, it concluded that the evidence showed that the Xcel project would
“cause a reduction in the market value of the residential homes adjoining the
line.” App. p.19 (Finding 22). The basis
for the decline in value encompassed aesthetic concerns, including the
increased height of the new power lines and its greater visibility to adjoining
homeowners and the neighbors, as well as the fears of health risks associated
with EMF.
The Court
also questioned the “qualifications” of the real estate agents. App. p.119.
The Court disregarded that the evidence of diminishment of property
values included data from Capital Appraisals, which noted a number of
deficiencies in a report submitted on behalf of Xcel, which prompted the
appraisal company to observe that “the reduction in property value and longer
selling times which are mentioned in the report [Xcel-commissioned],
underestimate the effect of power lines on property value.” App. p.11.[15]
The
Council is not required to follow strict rules of evidence for expert witness
testimony. See Rule 702,
Since
the Court overlooked the other expert testimony showing diminution in value,
its views that the real estate testimony “should not have been given much
weight” is baseless. The testimony of
the local real estate agents supplemented the other expert testimony and did
not stand alone. The amount of weight,
if any, to give to the testimony was a matter to be determined by the City
Council, not by the Court in second-guessing the Council. Honn
v. City of Coon Rapids, supra; Larson v. Washington County, supra. The evidence about project values was
disputed. On a motion for Summary
Judgment, the evidence must be viewed in the light most favorable to the
City. Therefore, the Court erred in
deriding the witnesses who testified about the negative effect on property
values and reaching its own judgment of which conflicting evidence to credit.
The
Court also determined that the City’s decision was erroneous because its
findings did not reference a property value study prepared by Colliers Towle Real Estate, which showed a .5% depreciation in
property values, within a 1% tolerance for errors of surveys of this type. App. p.118.
The Trial Court determined, from its review of the record, a decrease of
no more than .5% in property values of homes near the new power line, which it
regarded as de minimus.
But,
even a .5% (one half of one percent) decline in property values is not nominal. The City has an assessed value of
$110,296,200, which, like most assessed value, is much lower than the actual
market value. Thus, a .5% decline in
property values across the board could result in the diminution of about
$550,000 in assessed valuation. There
are 251 homes in the community.
Spreading a .5% decline among all of them may result in a diminution of
their property of about $2,200 each.
According to Capital Appraisals, the decline in property values would be
much greater for the homes that are closest to the power line, which could
suffer a much more sizeable debasement than the average diminution of $2,200
per residence. App. p.19 (Finding 19).
The
City was not compelled to accept some of the conflicting evidence over the
other. Faced with competing evidence,
the Council chose to credit Capital Appraisals, these three local real estate
agents, and individual property owners, who testified to greater diminution in
property values, and the Council’s determination should be accorded deference,
rather than “weighed” by the Court.
The
testimony from the certified real estate appraisal company, real estate
experts, and individual property owners provides a “rational basis” to support
a determination of adverse impact upon property values. Hubbard
323 N.W.2d at 764. Accordingly, the
Trial Court’s determination that the CUP was “arbitrary and capricious” on
grounds of a lack of insufficient evidence of adverse impact on property values
was erroneous and should be reversed.
3.
The
adverse health risks associated with the project also form a rational basis for
denying the CUP.
Finally,
the City denied the CUP on grounds of potential adverse health effects due to
increased exposure to EMF resulting from the project. App. p.19-28 (Findings 23 – 71). The City based its determination on
voluminous scientific and medical documents, supplemented by testimony of
experts such as Dr. Blank and Dr. Havas and local
physicians, as well as professional studies reflecting that increased exposure
to EMF is associated with health risks, such as leukemia in children, brain
cancer, miscarriages, neurological problems, Lou Gehrig’s
Disease, and other afflictions.
Findings,23-71.
The
District Court mischaracterized the testimony of both scientific experts, Dr.
Blank and Dr. Havas.
It dismissed the view of Dr. Blank with the observation that he “relies”
on a 1999 study conducted by the Natural Institute of Environmental Health
Services (NIEHS) which concluded, at that time, that EMF exposure from
transmission lines does not represent a potential for significant adverse
health impact. App. p.121. This constitutes a gross distortion of his
extensive testimony, numbering 12 pages in the record. He mentions the NIEHS study, in passing, only
thrice, in two of 19 passages, comprising barely 10% of his testimony. App. p.38.
The
Court also incorrectly reported the testimony of Dr. Havas,
characterizing her as having focused on the effects of EMF from small household
appliances. App. p.120. In fact, she primarily testified about animal
studies, not appliances. App. p.38.
The
impact of EMF on health is a contentious and evolving subject. Not surprisingly, the record contained
conflicting testimony on the issue.
While the topic is debatable, the Council had before it, as noted above,
ample evidence reflecting potential adverse health impact and, based upon that
evidence, chose to deny the CUP, for that reason, along with the others. This constituted a permissible reason to deny
the CUP. C.R. Investments, Inc. v. Village of Shoreview, 304 N.W.2d 320, 324
(
The
Trial Court relied heavily upon the City’s adoption of the determination by
CAI, Xcel’s paid consultant that there initially will be “substantial reduction
in EMF levels” following construction of the new power line. App. p.120.
But the Court disregarded Xcel’s own projection, which showed the
long-range impact of EMF resulting from increased power uses over time, a fact
the City rationally relied upon in its decision to deny the CUP. App. p.25 (Findings 52, 54).
This
view rationally flows from much of the evidence in the record. For example, the California Department of
Health Services conducted a 7 year, $9 million review of the health impact of
magnetic fields associated with transmission power lines. It concluded that the linkage between these
fields and an enhanced risk for contracting disease was a statistical
certainty. It also noted a possibility
of up to 95% that EMF cause birth defects, low birth weight, neonatal
problems, and cancer generally. App.
p.25 (Findings 55 – 57). Contrary to
Xcel’s assertion, the report states that EMF may cause specific diseases and a
95% likelihood of a causal relationship to specific afflictions.
The
Trial Court erred in finding that the new power line would reduce EMF
intensities by as much as 80%.
App.p.122. The Council made no
such determination. The findings cited
by the Court merely report upon an example set forth by Xcel’s paid
representative, CAI. The example
overstates the amount of possible reduction in EMF since it assumes currents in
the present line substantially exceed the actual maximum currents. The assumed currents in the proposed line are
less than the expected currents. App.
pp.20-22 (Findings 25 – 33). Further,
Xcel data suggest that, in a few years, the EMF levels will return to close to
their present status, if not exceed them.
App. p.20 (Finding 25).
The
District Court apparently was content to rely upon outdated research submitted
by Xcel questioning the impact of EMF on health dating back to 1997, while
disregarding the subsequent reversal of that skepticism in the past few years,
which were part of the contemporaneous record before the City Council. The NIEHS study, relied upon by the Court to
show insufficient linkage of EMF exposure and diseases, was subsequently called
into doubt by the California Department of Health reports. App. p.14 (Finding 70).
The
The
Trial Court dismissed the
More
fundamentally, the California Health Department, in its EMF Project on Breast
Cancer, addressed this issue, noting that:
[I]f
one were to be certain that the epidemiological associations were causal, the
population mortality would be more than that from many regulated environmental
agents. If one were to adjust these
numbers by one’s degree of confidence in causality, [the result] would still
not be trivial in the regulatory framework.”
App. p.28 (Finding 70, Executive Summary, p.
16).
But
even if a small number of people experience health problems, especially severe
ones like cancer, it would be rational for the Council to decide that the risk
outweighs the benefits of the new power line, as it did in fact do. App. p.33 (Conclusions D and E). In derogation of the Council’s authority, the
Trial Court re-evaluated the conflicting scientific evidence and concluded that
the documentation and evidence relied upon by the City Council was wrong.
At a
minimum, the Court recognized that there were conflicting opinions, and that
“statistical studies in the human population suggest there might be a problem
with EMF.” App. p.121. This alone is sufficient to justify the City
Council’s denial of the CUP and negates the Trial Court’s conclusion that the
City Council acted in an “arbitrary and capricious” manner by determining an
absence of potential harmful effects due to exposure to EMF from the power line
project. Since the matter is rationally
debatable, the City Council was entitled to reasonably base its decision upon
facts in the record before it.
The
Trial Court also misguidedly rejected any potential adverse health impact upon
the basis that the projected double-circuit line would reduce EMF exposure
initially by 80% compared to the existing single-circuit line. App. p.122.
But the Council took this into consideration and determined that even
these reduced levels exceed acceptable safety levels. App. pp.25-26 (Findings 52, 59-60). More significantly, the Council was concerned
that the greater exposure that would unquestionably occur in the future with
greater demand levels leading to increased current flow and higher EMF emission
levels and unsafe exposure associated with childhood leukemia, cancer, and
other afflictions, especially to those already susceptible to those illnesses,
involving those Sunfish Lake residents living near the existing line. App. pp.25-26 (Findings, 55-59).
The
record before the Court is barren of any suggestion by Xcel that power lines
are entirely safe. Nor has Xcel denied
an enhanced risk associated with living adjacent to them. Rather, it relied upon the assertion that the
“cause” of this risk has yet to be identified.
In short, it asked the Trial Court to do what Xcel is unwilling to do on
its own accord, expose people to an enhanced chance of contracting serious and
deadly diseases. Because the record
rationally supported the Council’s determination that the CUP would expose
residents of the community to increased and unacceptable health risks, its
denial of the CUP must be upheld on this ground alone.
4. Summary of Council’s
decision
In
sum, the District Court mistakenly decided that the City Council’s decision as
“arbitrary, capricious, and unreasonable.”
It is mind-boggling to imagine a process less arbitrary. The Council based its decision upon the
unanimous recommendation of its Planning Commission, which reviewed the issue
in three long sessions in which it received testimony from Xcel and opponents.
The
Sunfish lake City Council was far from capricious. Essentially the same question considered by
The
Trial Court erred in substituting its judgment for that of the Council or the
potential adverse health effect of the CUP project. The City Council rationally based its
determination on the record that, as the Trial Court agreed, there is some
likelihood, even though debatable, that the project will cause health risks,
especially in the future as exposure to EMF increases due to a rise in
electrical use. Since increased exposure
to EMF poses health risks and the degree of those risks is a disputed fact
issue, the Council was entitled to rely upon the evidence of the experts who
said it would, and its determination was factually-based, not fanciful,
arbitrary, or capricious.
For
the above reasons the Order permitting intervention of the Power Line Task
Force, Inc. was proper and should be affirmed.
The Trial Court erred in dismissing the case with prejudice, and its
ruling on the merits and Mandamus directing issuance of a Conditional Use
Permit was contrary to law and should be reversed and Summary Judgment granted
in favor of dismissal of the lawsuit as originally sought by the City and
joined by the Intervenor. Reversal of
that determination would negate the express predicate of the settlement
agreement and require rescinding the improperly – issued CUP.
MANSFIELD, TANICK &
COHEN, P.A.
Dated:
Marshall H. Tanick (108303)
1700 Pillsbury Center South
(612) 339-4295
ATTORNEYS FOR APPELLANT POWER LINE TASK
FORCE, INC.
LAW OFFICE OF CHRISTOPHER THOMAS JOHNSON
Christopher Thomas Johnson (0303744)
P.O. Box 86
(612) 386-8743
[1]
All references to the
City Council’s Resolution denying the CUP are designated as “Finding ____” or
“Conclusion ____.”
[2] The biological impact of a
magnetic field varies with its frequency.
Power lines emit very low frequency magnetic fields. These fields have
been studied for more than three decades and, therefore, much more is known
about them then the high frequency fields associated with cellular
telephones. The findings of heightened
risk for EMF are not relevant to the risk, if any, associated with cell phone
emissions.
[3] The groups that have
recognized the relationship between EMF and serious diseases, many of whose
studies were part of the administrative record before the Sunfish Lake City
Council, include the World Health Organization, the British Journal of Cancer,
the United Kingdom Government Study of Childhood Leukemia, the German
Environmental Ministry on Childhood Leukemia, Japanese National Cancer Center,
Japan National Institute for Environmental Studies, the Canadian National
Research Council on EMF, the Washington State Health Report on Childhood
Leukemia, the California EMF Project on Childhood Leukemia, two studies by the
California EMF Project on Miscarriages, the California EMF study on Breast
Cancer, and others. App. pp.38,40,44
(Finding 70).
[4] In its ruling, the Trial
Court erroneously referred to a survey of
[5] The Task Force is the only
Appellant in this case; the other two individual Intervenors are not parties to
this proceeding.
[6] Xcel released the City from
any claims for damages and legal fees arising from the lawsuit or any act or
omission of the City in connection with Xcel’s applications. App.
pp.134-135. Although the CUP has been
issued, construction has not begun on the new replacement line.
[7] The Task Force requested
re-consideration, App. p.181, which the Trial Court refused. App. p.183.
[8]
The City and Xcel raises, in their Joint Statement of the Case, the contention
that the Task Force should not have been allowed to intervene in this
case. But the City did not take any
position regarding intervention in the Trial Court proceedings. App. p.203.
Since it did not raise the issue below, the City is barred from making
the contention for the first time on appeal.
Oans v. Allstate Ins. Co, 617 N.W.2d 401 (
[9] The U.S. Supreme Court, in
a different context, recently upheld the right of non-intervenors, who are not
named parties in a class action, to appeal the settlement and dismissal of a
class action case, even though they have not intervened in the action. Devlin
v. Scardelletti, 122 S.Ct.
2005 (2000). While Devlin turned on characteristics of class action litigation, the
Task Force has an eminently stronger posture in this case, where it is formerly
been granted Intervenor status and, therefore, is entitled to participate fully
as a party in the lawsuit.
[10] Although it had written two
letters to the Trial Court expressing opposition to the dismissal, App. pp.
146-147 and pp. 162-163, the Task Force was not informed that an order of
dismissal was signed on
[11] The EQB could have declared
itself the “Responsible Government Unit,” allowing it to approve or disapprove
the Xcel project. But it declined to do
so, leaving the matter to the local authorities. App. p.27.
[12] The Trial Court did not discuss
or mention this fundamental standard in its ruling. App. pp.99-126.
[13] Xcel also failed to obtain
a Route Permit from the EQB, also as required for a “large energy facility,”
such as this project, after
[14] The document upon which
Xcel relies to justify the need for the project, the report prepared by its
paid-for designee, CAI, is based wholly on the premise that the project would
run the 14-plus mile length between the
[15] The report negating
diminution of property values was paid for by Xcel; the Capital Appraisals
report challenging that conclusion was submitted voluntarily and without
compensation.