STATE OF
IN COURT OF
APPEALS
CASE NO.
C3-02-1409
Power Line Task Force, Inc.
Appellant
v.
Northern States Power
Company
d/b/a Xcel Energy, Inc. and
City of
Respondent
BRIEF OF APPELLANT
|
Marshall
H. Tanick (108303) 1700
Pillsbury Center South (612)
339-4295 and LAW OFFICE OF CHRISTOPHERTHOMAS
JOHNSON Christopher
Thomas Johnson (0303744) P.O.
Box 86 (612)
386-8743 ATTORNEYS FOR APPELLANT POWERLINE TASK FORCE, INC. |
BRIGGS & MORGAN, P.A. Jack
Y. Perry (209272) 2400
IDS Center (612)
334-8400 and Of Counsel Harold
J. Bagley (3906) Assistant
General Counsel Xcel
Energy (612)
251-4586 ATTORNEYS FOR RESPONDENT NORTHERN STATES POWER COMPANY d/b/a XCEL ENERGY * * * * GREEN ESPEL P.L.L.P. Clifford
M. Green (37436) William
P. Hafner (258349) (612)
373-0830 |
|
|
ATTORNEYS FOR RESPONDENT CITY OF |
B. The Sunfish Lake Proceedings
F. Subsequent Settlement and Dismissal
I.
THE TASK FORCE PROPERLY INTERVENED IN THIS
CASE
B. The Intervention Was Proper Under Rule 24
II. DISMISSAL OF THE CASE WITH PREJUDICE
VIOLATES RULE 41.01(B) AND WAS IMPROPER
B. Dismissal of the lawsuit with
prejudice was improper
C. The City had a rational basis for denying the
CUP.
1. The record reasonably reflects an absence of a
need for the project.
a.
A Required Certificate From the PUC was Lacking
b.
The Evidence About Need Was Conflicting
c. The Project
was not a non-conforming use
2. The diminution of property values constitute a rational basis to deny the CUP.
3. The adverse health risks associated with the project also form a rational basis for denying the CUP.
4. Summary of Council’s decision
I.
Was it proper to permit intervention under
Rule 24,
The
Trial Court held in the affirmative, allowing the group to intervene under Rule
24 of the Minnesota Rules of Civil Procedure.
Appellants maintain that the decision of the Trial Court was
correct. Norman v. Refsland, 383 N.W.2d 673, 678
(Minn. 1986); Costley v. Caromin House,
Inc., 313 N.W.2d 21, 28-29 (Minn. 1981); Snyder’s Drug Stores, Inc., v. Minn. State Bd. of Pharmacy, 221
N.W.2d 162, 166 (Minn. 1974); BE & K Constr. Co. v. Peterson, 464 N.W.2d 756 (Minn. Ct. App.
1991).
* *
* * *
* * *
* * * *
II. Did the Trial Court err in dismissing this lawsuit with prejudice, over the objection of the Intevenor, without providing terms or conditions that are “proper” to protect the right of Intevenor to appeal from an earlier mandamus decision entered by the Court?
The
Trial Court held in the negative, ordering that the lawsuit be dismissed with
prejudice and without providing any terms or conditions to permit the Intevenor to appeal from the earlier decision.
Appellant
maintains that the decision of the Trial Court dismissing the case with
prejudice was erroneous. Lang v. William Bros Boiler & Mfg. Co.,
85 N.W.2d 412 (
* *
* * *
* * *
* * * *
III.
Did the Trial Court err in directing the
City of
The Trial
Court ruled in the affirmative, holding that the decision by the City Council
of Sunfish Lake to deny a CUP was arbitrary, capricious, and unreasonable and
ordered the City to grant the application.
Appellant
maintains that the decision by the Trial Court was erroneous and should be
reversed. Interstate Power Co., Inc. v. Nobles County Bd. of Comm’rs,
617 N.W.2d 566 (Minn. 2000); Honn v. City of Coon
Rapids, 313 N.W.2d 409 (Minn. 1981); State
v. Larson Transfer & Storage, Inc., 246 N.W.2d 176 (Minn. 1976); Beck v. City of St. Paul, 231 N.W.2d 919
(Minn. 1975).
STATEMENT OF THE CASE
This
is an appeal from a determination by the Dakota County District Court, the
Honorable Rex Stacey, concerning an effort by Northern States Power Company
d/b/a Xcel Energy (“Xcel”) to replace a single-circuit electric power line with
a new more intensive double-circuit transmission structure running through the
City of Sunfish Lake. After its
application for a Conditional Use Permit (CUP) to replace the line was denied
by the City, Xcel sued the City seeking Mandamus directing it to grant the
application.
The
City initially opposed the lawsuit. It
was joined by the Power Line Task Force, Inc. (“Task Force”), an organization
consisting of residents effected by Xcel’s proposal, as well as two individual
homeowners, who sought to intervene in the action. The Trial Court allowed them to intervene
under Rule 24 of the Minnesota Rules of Civil Procedure.
The
Trial Court, on a motion for Partial Summary Judgment by Xcel, ordered the City
by Mandamus to issue the CUP for replacement of the power line. The Intervenors intended to appeal, but in
the meantime, Xcel and the City without involvement of the Intervenors, entered
into a Settlement Agreement. Under the
Agreement, the City granted the CUP, and the City and Xcel, without the
participation of the Intevenors, stipulated to a
proposed Court order dismissing the lawsuit with prejudice.
The
Intervenors, who were not signatories to the settlement or stipulation, opposed
dismissal of the lawsuit with prejudice.
The Court, without notice to Intervenors, signed the order requested by
the City and Xcel to dismiss the lawsuit with prejudice. Rule 41.01(b) Minn. R. Civ.
P. states that a lawsuit may not be dismissed with prejudice unless all parties
agree or the Court does so upon terms and conditions that are “proper.” After signing its Order, it conducted a
hearing at which Intervenors requested that the matter not be dismissed with
prejudice without protecting their right to appeal from the prior Mandamus
ruling.
The
Trial Court adhered to its prior ruling and ordered the lawsuit dismissed with
prejudice without any other terms or conditions. Judgment was then entered dismissing the
lawsuit with prejudice.
The
Task Force brought two related appeals.
The present appeal challenges: dismissal of the lawsuit with prejudice
without “proper” terms to protect the rights of the Intervenor. A separate appeal, C0-02-1285, contested the
Mandamus ruling of the Trial Court. A
Panel of this Court, on
STATEMENT OF THE FACTS
This
case concerns the attempted replacement by Xcel of an existing single circuit
power line with a new double-circuit structure bearing a different, more
intensive power line running through the community of
In
the late 1990’s, Xcel announced a project seeking to build a new double-circuit
of 115 kV transmission line covering a distance of 14.76 miles from the Red
Rock Substation in Newport to the Wilson Substation in Bloomington. App. p.15 (Finding 9), passing within 50 feet
of about 208 housing units, including apartments, including several homes in
The
existing line, supported by wooden H-frame structures ranging from 51 – 85 feet
high, is part of Xcel’s transmission grid delivering electric power to
customers throughout the Twin Cities metropolitan area. App. p.17 (Findings 10-11). Xcel sought to replace that line with steel
structures supporting double-circuit lines ranging from 80-110 feet high. App. p.17 (Finding 12). In addition to the greater height, the
proposed double circuit would have concrete foundations drilled into the ground
at a depth in excess of 30 ft, in lieu of the current wooden poles that are
embedded without permanent foundations.
The
Minnesota Public Utilities Commission (“PUC”) earlier had declined a request by
a group of citizens to remove the existing single-circuit power line. See In the matter of the Complaint regarding the safety of Northern States
Power Company’s transmission lines in the Southeast Metro Area, Docket No.
E-002/C-99-902, 2000 WL 772434 (
The
Minnesota Environmental Quality Board (“MEQB”) also declined to require the
submission of an Environmental Impact Statement in conjunction with the
proposed project. App. p.8. The MEQB could have declared itself the
“Responsible Government Unit” and passed upon the merits of Xcel’s application,
but chose not to do so, nor did it reach a judgment on whether a Statement was
needed. Stating that it was not the
“responsible governmental authority to make that determination,” the agency
agreed with the PUC that the project is “subject to local control, including
Conditional Use Permits.”
Xcel
then sought approval from the various communities through which the replacement
line would run, including
B.
The
Although
the existing line is “grandfathered” as a non-conforming use, the proposed
double circuit replacement requires a CUP and site approval under the City’s
Zoning Code, City Code § 1224.05. The
criteria for granting or denying the CUP include the protection of the public
health, safety, and welfare, the health effects, impact on surrounding
properties and need for the project.
City Code, §§ 1204 and 1224.
The
City has a multi-step process to replace or reconstruct a transmission
line. First, a CUP has to be obtained
for the project as a whole and its route, if approved, the site and building
plan approval must be obtained. City
Code § 1224.05. In addition to seeking a
CUP, Xcel also sought a minor variance from the City’s requirement that poles
be 60 ft from houses and conductors be at least 37.5 ft from homes, although
the 50-foot width of the easement would remain unchanged. App. p.17 (Finding 16).
Under
the Sunfish Lake Zoning Code, when an application is made for a CUP for a
transmission line, the City Counsel is to consider other potential routes in
addition to that proposed by the applicant.
City Code § 1224.05 (F) and (G).
Scrutiny of the project consists of public hearings before the Planning
Commission, which makes a recommendation of the City Council for approval or
denial. Following public hearings, the
council makes a decision. If the
application is approved, the council next addresses a proposal for site
specific construction details, known as the site and building plan stage; if
the CUP is not granted, no further action is taken.
Three
of the effected communities, including
Significant
health issues pertained to the replacement power line upon those living
nearby. Power frequency magnetic fields
arise from electric currents. They are
part of the electromagnetic field (EMF) associated with every power line. The intensity of a magnetic field is a
function of the amperage going through the line. The greater the current transmitted, the
greater is the magnetic field intensity.
The intensity of a magnetic field varies with the distance from the
source. App. p.19 (Finding 23.)
The
proposed line would carry a great deal of current, up to 1600 amps in each of
its two circuits. App. pp.16,20 (Findings
9, 24-25). It would pass within 30 feet
of houses, much closer than Xcel’s own practice for new lines according to
Xcel’s own estimates, and would expose the residents of adjacent homes to
magnetic fields more than 40 times more intense than the average residential
fields in the United States.
Health
hazards posed by power lines have been of concern since 1971. [2] The issue is not one
of “junk” science. It has been treated
seriously by the established scientific community, physicians, and national and
international health organizations. The
adverse health effects from exposure to EMF include increased likelihood of
child leukemia, ameotrophic lateral sclerosis (ALS or
Lou Gehrig’s Disease), neurological disorders, breast
cancer, and miscarriages, among other afflictions, especially among those
already susceptible to those diseases.
App. pp.25-26 (Findings 55 – 60).
Debate
existed for many years within the scientific community regarding the
relationship between EMF and those diseases.
There were inconsistencies in the epidemiological research: some studies found a linkage and others did
not. But in 2000, in three independent
studies, scientists reexamined earlier investigations and concluded that a link
exists between EMF and a heightened risk of contracting serious diseases. App.
p.28 (Finding 70). As a result, credible
and strong scientific data shows that exposure to heightened EMF is
epidemiologically linked with an enhanced risk of contracting serious disease,
a view shared by many officials and leading government authorities, including
some who have modified their earlier doubts regarding the existence of this
linkage. [3]
The
double-circuit line proposed by Xcel initially would reduce EMF in comparison
to the existing single-circuit line. App.
p.22 (Finding 34). But opponents of
Xcel’s plan, supported by independent experts, submitted substantial
information that the new power line would, based upon future demand, result in
an increase in amps and EMF that could endanger the health of those living near
the site. App. p.25 (Findings 54 –
55). Some of this testimony was
furnished by Dr. Martin Blank, a Microbiologist and Professor of Physiology at
Their
views, along with voluminous supporting documents, were provided to the
Steering Committee and were part of the record used by the Sunfish Lake City
Council in evaluating Xcel’s request for a CUP.
App. pp.35-44. Documentation also
was submitted from MSB, an independent engineering consulting firm, casting
doubt upon Xcel’s projections concerning the intensity of power line usage and
resulting EMF. App. p.38. Four practicing physicians (a surgeon,
OB/GYN, radiologist, and general practitioner) also testified about potential
health effects resulting from increased future exposure to EMF from the
proposed new line.
Xcel
submitted testimony of one health-related consultant and a mid-level official
from the Minnesota Department of Public Health.
In contrast, Jan Malcolm, the Commissioner of the State Department of
Public Health, wrote that “[f]rom a public health
standpoint, I am concerned about the level of magnetic field exposure (EMF) to
which certain residents are now and will continue to be subject,” noting that
Xcel’s project was anticipated to generate much greater exposure levels than
those in the MEQB studies.
The
Mayoral Steering Committee did not adopt any report nor issue conclusions or
recommendations of its own. The Sunfish
Lake Planning Commission held three lengthy hearings in December, 2001 and
January, 2002, consuming about ten hours, and received more than 100 documents,
comprising in excess of 2,000 pages, along with live testimony, forming the
voluminous administrative record in this case.
App. p.43. During the proceeding,
Xcel orally stated, without supporting documentation, that it would defer its
14-plus mile project and limit the proposal to a 6.36 segment running from the
Red Rock Substation in
The
City considered three available options: an above-ground double circuit 115 kV
transmission line; a below-ground double circuit 115 kV transmission line; a
below-ground double circuit transmission line; or denial of the project. App. p.18 (Finding 17). Xcel maintained that the project was
necessary and that a below-ground line would be economically unfeasible,
costing some $6.5 million, compared to $500,000 for an above-ground structure. App. p.23 (Findings 36-37).
Opposition
to the project focused on several issues: diminution of the value of adjoining
properties, adverse health effects due to increased exposure to EMF, and lack
of need for the project. App. p.18
(Finding 18).
The
City was guided through the process by its City attorney, who emphasized the
importance of basing any action on facts in the record and drafted alternative
proposed findings of fact, one supporting approval of the CUP and the other
containing supporting denial, which were made available to Xcel members of
public, including opponents of the project, who offered extensive comments to
the alternate versions, which were modified as the process progressed. On
The
Findings included a determination that the project “will cause a reduction in
the market value” of homes in the vicinity of the power line. App. p.19 (Finding 22). In evaluating health concerns, the Council
noted that several residents near the power line have “health problems” that
may be aggravated by EMF exposure, App. pp.25-26 (Finding 58), that EMF
exposure will increase over time, as demand for power rises and the increase
will “have adverse health effects,” including a greater likelihood of child
leukemia, ameotrophic lateral sclerosis (Lou Gehrig’s Disease), neurological disorders, breast cancer
and miscarriages, among other matters, especially among those already
susceptible to those afflictions. App.
p.26 (Findings 59-60). The Council also
determined that it was not reasonable to permit the “unjustified [health] risks
. . . of constant and cumulative exposure to EMF,” that would result from the
project. App. p.26 (Findings
62-63). The Council also found that Xcel
had not “shown a demonstrated need” for the project based upon the lack of any
certificate need from the PUC or determination from that agency that a Certificate
of Need was not required. App. p.30
(Findings 86, 89).
The
City made supporting Conclusions that the project “will cause a reduction of
the market value” of homes in the area, App. p.33 (Conclusion F), that
“credible” evidence exists of “adverse” health effects stemming from the
project, App. p.33, (Conclusions D and E), and that there was no showing of a
“need for the project” at the present time.
App. p.34 (Conclusion H).
Coupled
with its Findings and Conclusions, the Council identified a voluminous record
of 109 items of testimony, reports, and other materials that constituted the
record and support its determination, including appraisal materials concerning
real estate values; numerous reports about adverse health effects from EMF,
including testimony from two experts, Dr. Blank and Dr. Havas,
and four local physicians, and numerous other data gathered during the process
as well as from hearings from other nearby cities regarding efforts by Xcel to
replace its power line in those communities, too. App. pp.35-44.
Xcel
sued the City on
Xcel
brought a Motion for Partial Summary Judgment seeking Mandamus for issuance of
a CUP. App. pp.81-82. The City made a cross-motion for summary
judgment. App. p.96. The Task Force and two individual residents
timely sought intervention as Defendants.
App. pp.97-98. At a hearing on
the cross-motions for Summary Judgment, the Court permitted them to intervene,
over objection of Xcel. App. ____. Although granted the right to intervene, the
Task Force was not allowed by the Court to make any argumentation or submit a
brief at the hearing on the Motions.
App. p.102 (Trial Court Memorandum, p.4).
On
In its
ruling, the Court determined that the City’s denial of a CUP was arbitrary,
capricious, and unreasonable. Paying
homage to the “very fine efforts” of City officials, App. p.101 (Trial Court
Memorandum, p.3), the Court reached the “inescapable conclusion” that the
denial of the CUP was “unauthorized, unreasonable, arbitrary and
capricious.” Addressing Xcel’s motion
for Summary Judgment, the Court declared that the “underlying facts are not in
dispute.”
The Court
also determined that Xcel had established need for the replacement line circuit
and that it did not need a Certificate of Need from the PUC nor a determination
by the Commission waiving a certificate since the statutory requirement for a
Certificate of Need, pursuant to Minn. Stat. §216B.242 subd.6, only applies to
projects undertaken on or after August 1, 2001 and that Xcel had initially
sought the permit prior to that date, which rendered the statute
inapplicable.
The Court
concluded that denial of the CUP was unreasonable because the City really
wanted “removal of the [existing] line altogether.”
F.
Subsequent
Settlement and Dismissal
The Task Force,
as Intervenor, planned to appeal.[5] The City and Xcel then began discussions to
resolve a case through issuance of a CUP.
The Task Force objected, urging that the Mandamus order be appealed. The Council indicated it would appeal if the
Task Force would post a bond of $135,000 to cover the City’s legal
expenses. App. pp.127-129. The Task Force agreed and arranged for a
letter of credit. App. p.130. The City recanted and, rather than appealing,
on July 2, 2002, by a vote of 4-1, flip-flopped and entered into a settlement
with Xcel July 2, 2002, which was explicitly predicated upon the Mandamus
ruling of the Trial Court. App.
pp.130,139.
In the
settlement, the City agreed to furnish a CUP in exchange for minor
consideration by Xcel, and the parties further agreed to stipulate to dismissal
of the lawsuit with prejudice.[6] The Task Force, which was not included in
discussions or a signatory to the arrangement, opposed the settlement because
it believed that the Mandamus ruling that predicated the settlement was
erroneous and should be appealed.
Xcel and
the City presented the stipulation to the Trial Court, which entered an Order
on
The Task Force then brought this appeal, claiming that the Trial Court erred in dismissing the case with prejudice without providin