MEMORANDUM
FROM :
TO : Power
Line Task Force
DATE :
RE :
Xcel Energy has announced that in April, 2003 it will
begin construction of its planned new double circuit, 115kV, 14.6 mile transmission
line in
Xcel first announced its plans in 1999. Pursuant to the then applicable law,
transmission line siting decisions were subject to local community
control. Accordingly, in the fall of
that year, Xcel applied to
As of
The
No
person may construct a high voltage transmission line without a route permit
from the [Minnesota Environmental Quality] board. A high voltage transmission line may be
constructed only along a route approved by the board...”
--Minn. Stat.
§116C.57, subd. 2.
The term “high voltage transmission line” is
defined as
a conductor of electric energy and associated
facilities designed for and capable of operation at a nominal voltage of 100
kilovolts or more.
Section
116C.52 Subd. 8, defines “Route" as
“the location of a high voltage transmission line between two end points. The route may have a variable width of up to
1.25 miles.” There is no minimum route length.
There is not, nor has there ever been, a provision for the
MEQB’s grandfathering of power lines for which
planning was underway before the effective date of the 2001 law. Xcel has previously claimed that such a
provision applied to this line,[1]
but the provision it cited applied only to the Public Utilities Commission’s process for establishing a list of
priority electric transmission projects, not its certificate of need
process. See Minn. Stat. §216B.2425, subd. 6, and
An attempt was made to have the 2002 Legislature amend
Minn. Stat. §216B.243,
which relates to the need to acquire a certificate of need for a “large energy
facility” from the PUC. Language was proposed to exempt from the
certificate of need process projects for transmission lines with capacities
between 100 and 200 kilovolts for which application was pending before a local
unit of government, the MEQB, or the PUC on August 21, 2001.[2] The proposed amendment was struck from the
language of the bill before it was passed.[3]
I want to emphasize that the exemption discussed above
applies only to the MPUC process, not the MEQB.
Minnesota Statutes §116C.575
provides for an alternative review process by the MEQB. This process is similar to that provided by §116.57. In requires that the MEQB issue a route
permit, but it has somewhat reduced requirements for documentation. The “alternative review process,” however,
requires the permit applicant to notify the MEQB chair at the time of application whether it wishes to proceed under §116C.57 or §116C.575. This was not done.
Additionally, Minnesota Statute §116C.576
provides that Xcel could, as an alternate to §116C.57 and §116C.575,
apply to the local communities for siting permission. The communities can, if they choose, request
the MEQB to assume jurisdiction.
Accordingly, Xcel’s failure to apply for, and receive from
either the MEQB or the local communities the mandated route permit means any
construction on this new line would violate the law.
In my view,
therefore, action can and should be taken to prevent any siting or construction
of this new transmission line until and unless a route permit is sought and
received, from either the MEQB or the local communities as required by Minn.
Stat. §116C.57, §115C,575, and §116C.576.
[1] Xcel Energy’s Memorandum of Law in Support of Its Motion for Summary Judgment, Statement of “Undisputed” Facts, p. xxvi, April 12, 2002.
[2] H.F. No. 2972, 2nd Engrossment: 82nd Legislative Session
(2001-2002) Posted on
[3] H.F. No. 2972, 3rd Engrossment: 82nd Legislative Session
(2001-2002) Posted on