DISTRICT COURT
FIRST JUDICIAL DISTRICT
Case Type: Other Civil
Court
File No. MC 03-003400
STATE OF
Power Line Task
Force, Inc., a
Plaintiff,
v.
Northern States
Power Company, d/b/a Xcel Energy, a
Defendant.
The above-entitled matter came on for Plaintiff’s Motion for
Summary Judgment and Defendant’s Motion to Dismiss
before the undersigned, a Judge of the above-named Court, on
Richard Morgan, Esq. and Emily Murphy, Esq., appeared on
behalf of the Plaintiff, Power Line Task Force, Inc. (“Power Line”). Jack Perry, Esq. appeared on behalf of the
Defendant, Northern States Power Company d/b/a Xcel Energy (“Xcel”).
PROCEDURAL HISTORY
Plaintiffs contend that Summary Judgment under Minnesota
Rule of Civil Procedure, 56.01, should be granted to Power Line as there exists no disputed issue of material fact that Defendant’s
proposed Southeast Metro Transmission Line project is a 115 kV line exceeding
ten (10) miles in length on which construction had not begun prior to
Defendant Xcel denies that the law requires it to apply
for a Certificate of Need or Route Permit, arguing the Southeast Metro
Transmission Line is less than ten miles in length because construction of the
line would occur in two (2) phases each less than ten miles in length. Later, in an
In Defendant’s Motion to Dismiss, it claims that applications
to local cities for zoning permits and Conditional Use Permits related to the
Southeast Metro Transmission Line satisfy the legal requirements for a
Certificate of Need and Route Permit because the zoning applications and
Conditional Use Permits were made prior to
After fully considering the oral and written arguments of
counsel, exhibits submitted, and applicable law, the Court makes the following
Findings of Fact and Conclusions of Law:
FINDINGS OF FACT
1. The
Minnesota Environmental Rights Act under Minnesota State Statute Section
116B.01, provides that an entity may maintain a civil action in the name of the
State of Minnesota for protection of the air, water, land or other natural
resources within the state from pollution, impairment or destruction.
2. The
3. The parties do not dispute that these
two laws became effective
4. It is also
undisputed that prior to the August 1, 2001 changes in the above-cited laws,
Xcel would not have been required to apply for either the Certificate of Need
or the Route Permit.
5. Both
parties agree that the proposed Southeast Metro Transmission line is a 115 kV
line.
6. Xcel’s documents indicate that the proposed
Southeast Metro Transmission Line project is a 14.7 mile transmission line
extending from Red Rock Substation, Stockyards Substation, Rogers Lake
Substation, the Airport Substation and the
7. A petition dated
8. Xcel’s documents
show that a concrete slab used to store heavy equipment was constructed at the
Red Rock substation prior to
9. As indicated by a letter sent to
homeowners dated
10. Xcel has never applied to the Minnesota
Public Utilities Commission for a Certificate of Need before beginning
construction on the Southeast Metro Transmission Line.
11. Xcel has
never applied to the Minnesota Environmental Quality Board for a Route Permit
before beginning construction on the Southeast Metro Transmission Line.
12. In 2002,
the Minnesota Legislature considered adding language to Minnesota State Statute
Section 216B.243, subdivision 8, the exemption paragraph for Certificates of
Need, exempting transmission lines of 115kV more than ten miles in length for
which an application had been approved by or was pending before at least one
local unit of government on August 1, 2001.
The Legislature never enacted this provision into law.
13. The
“application has been approved by or was pending before at least one local unit
of government on August 1, 2001” language relied upon by Xcel applies to a
separate statutory provision concerning public utility projects, commonly called
the Priority List statute, Minnesota State Statute Section 218B.2425.
14. Defendant
Xcel did not apply to all local units of government affected by the proposed
upgrade of the Southeast Metro Transmission Line project prior to
15. A
February 21, 2002, letter to non-party Great River Energy from John Hynes using
Minnesota Environmental Quality Board letterhead gave an opinion exempting a separate
project proposed by Great River Energy from the Route Permit statute because
the project “was begun” prior to August 1, 2001.
16. The above-referenced letter does not address
the issue of when or whether construction began on the exempted Great River
Energy proposed project for the purpose of Minnesota State Statute Section
116C.52, subsection 3.
17. Minnesota
State Statute Section 116C.02, subdivision 6, states that members of the
Minnesota Environmental Quality Board may not delegate their powers and
responsibilities as board members to any other person.
CONCLUSIONS OF LAW
1. Xcel’s
documents established that the proposed Southeast Metro Transmission Line is an
115kV line extending 14.7 miles.
2. Xcel’s
documents established that construction did not begin on the proposed Southeast
Metro Transmission Line until after
3. A
document provided by Xcel regarding the construction of a slab of concrete at
the Red Rock substation is not proof of construction on the Southeast Metro
Transmission Line, but rather proof of construction at a substation. According to Minnesota State Statute Section
116C.52, subdivision 8, a “route” is “the location of a high voltage
transmission line between two end points.”
The Red Rock Substation is the end point of the Southeast Metro
Transmission Line according to Xcel’s own documents. Construction at a substation is construction
at a “site”, or “the location of a large electric power generating plant” as
described under Minnesota State Statute Section 116C.52, subdivision 9. The statutory scheme separates “site”
construction from construction on a transmission line “route.”
4. No legislative
language exempting proposed high voltage transmission line
projects that had applications pending before at least one local unit of
government before
5. Legislative language exempting proposed
high voltage transmission line projects that had applications pending before at
least one local unit of government before
7. Therefore,
Xcel cannot rely upon the “application has been approved by or was pending before
at least one local unit of government on August 1, 2001” language found in the
Priority List statute under section 216B.2425 to the Certificate of Need statute
under section 216B.243 or the Route Permit statute under section 116C.57. Indeed, as to the
8. Applications
made by Xcel to local cities for zoning permits for zoning issues related to
the Southeast Metro Transmission Line are separate and distinct applications
and do not exempt Xcel from applying for and receiving a Certificate of Need or
Route Permit under sections 216B.243 and 116C.57 respectively.
9. The
February 21, 2002 letter to Great River Energy from John Hynes has no force and
effect because the letter indicates a staff member opinion rather than a board
ruling as required under Minnesota State Statute Section 116C.02, subdivision
6.
10. Furthermore, the
11. Therefore,
the
Environmental Quality Board
have never issued formal findings that Xcel is exempt
from applying for and obtaining a Certificate of Need or a Route Permit for the
proposed Southeast Metro Transmission Line.
12. Under section 216B.243, Xcel must apply to
the Minnesota Public Utilities Commission for a Certificate of Need prior to
beginning construction on the Southeast Metro Transmission Line.
13. Under section 116C.57, Xcel must apply to
the Minnesota Environmental Quality Board for a Route Permit prior to beginning
construction on the Southeast Metro Transmission Line.
14. Defendant Xcel admits that they have not
yet applied to either the Minnesota Public Utilities Commission or the
Minnesota Environmental Quality Board for the above-required permits.
15. The
aim of the environmental legislation found in Minnesota State Statutes Sections
116C.51 to 116C.69, enacted to complement the Minnesota Environmental Rights
Act under section 116B.01, was to harmonize the need for electric power with
the equally important need for environmental protection. Floodwood-Fine
Lakes Citizens Group v.
16. Section
216B.243 and Section 116C.57 are part of environmental legislation enacted to
ensure that a public utilities’ proposed changes in electrical power are
compatible with environmental concerns in Minnesota State Statute 116B.01.
18. Therefore,
Defendant’s failure to obtain the permits required by Sections 216B.243 and
116C.57 violates the Minnesota Environmental Rights Act under Minnesota State
Statute Section 116B.01.
19. Xcel’s
entry upon the private property of Power Line representatives to begin
construction of the Southeast Metro Transmission Line prior to applying for and
obtaining the requisite permits under Minnesota State Statutes Sections
216B.243 and 116C.57 is a trespass and invasion of privacy.
20. Power Line is
the prevailing party as defined by Minnesota Rule of Civil Procedure 56.01.
ORDER FOR JUDGMENT
Based upon the Findings of Fact, Conclusions of Law and
all the files, records and proceedings herein,
IT IS HEREBY ORDERED:
1. Plaintiff’s Motion for Summary Judgment
under Minnesota Rules of Civil Procedure, Rule 56.01, is hereby granted and
judgment is entered on behalf of Power Line Task Force.
2. Defendant’s Motion to Dismiss is hereby
dismissed.
LET JUDGMENT BE ENTERED ACCORDINGLY.
BY THE
COURT:
________________________________________
Karen
Asphaug
Judge
of District Court
Dated
this ______ day of November, 2003