Excerpts from Minnesota Chapter 116c regarding EQB oversight

(Subdivisions of particular interest are shown in italics)

 

 

116C.52 Definitions
Subd. 2.    Board.  "Board" shall mean the Minnesota 
 environmental quality board. 
Subd. 4.    High voltage transmission line.  "High 
 voltage transmission line" means a conductor of electric energy 
 and associated facilities designed for and capable of operation 
 at a nominal voltage of 100 kilovolts or more. 
Subd. 6.    Large electric power facilities.  "Large 
 electric power facilities" means high voltage transmission lines 
 and large electric power generating plants. 
Subd. 8.    Route.  "Route" means the location of a high 
 voltage transmission line between two end points.  The route may 
 have a variable width of up to 1.25 miles. 
Subd. 10.    Utility.  "Utility" shall mean any entity 
 engaged or intending to engage in this state in the generation, 
 transmission or distribution of electric energy including, but 
 not limited to, a private investor owned utility, cooperatively 
 owned utility, and a public or municipally owned utility. 
 
116C.53 Siting authority
Subdivision 1.    Policy.  The legislature hereby 
 declares it to be the policy of the state to locate large 
 electric power facilities in an orderly manner compatible with 
 environmental preservation and the efficient use of resources.  
 In accordance with this policy the board shall choose locations 
 that minimize adverse human and environmental impact while 
 insuring continuing electric power system reliability and 
 integrity and insuring that electric energy needs are met and 
 fulfilled in an orderly and timely fashion. 
Subd. 2.    Jurisdiction.  The board is hereby given the 
 authority to provide for site and route selection for large 
 electric power facilities.  The board shall issue permits for 
 large electric power facilities in a timely fashion.  When the 
 public utilities commission has determined the need for the 
 project under section 216B.243 or 216B.2425, questions of need, 
 including size, type, and timing; alternative system 
 configurations; and voltage are not within the board's siting 
 and routing authority and must not be included in the scope of 
 environmental review conducted under sections 116C.51 to 116C.69.
 
116C.57 Designation of sites and routes; procedures; 
  considerations; emergency certification; exemption. 
Subd. 2.    Route permit.  No person may construct a 
 high voltage transmission line without a route permit from the 
 board.  A high voltage transmission line may be constructed only 
 along a route approved by the board.  
Subd. 2a.    Application.  Any person seeking to 
 construct a large electric power generating plant or a high 
 voltage transmission line must apply to the board for a site or 
 route permit.  The application shall contain such information as 
 the board may require.  The applicant shall propose at least two 
 sites for a large electric power generating plant and two routes 
 for a high voltage transmission line.  The chair of the board 
 shall determine whether an application is complete and advise 
 the applicant of any deficiencies within ten days of receipt.  
 An application is not incomplete if information not in the 
 application can be obtained from the applicant during the first 
 phase of the process and that information is not essential for 
 notice and initial public meetings.
Subd. 2b.    Notice of application.  Within 15 days 
 after submission of an application to the board, the applicant 
 shall publish notice of the application in a legal newspaper of 
 general circulation in each county in which the site or route is 
 proposed and send a copy of the application by certified mail to 
 any regional development commission, county, incorporated 
 municipality, and township in which any part of the site or 
 route is proposed.  Within the same 15 days, the applicant shall 
 also send a notice of the submission of the application and 
 description of the proposed project to each owner whose property 
 is on or adjacent to any of the proposed sites for the power 
 plant or along any of the proposed routes for the transmission 
 line..... Within the same 15 days, the 
 applicant shall also send the same notice of the submission of 
 the application and description of the proposed project to those 
 persons who have requested to be placed on a list maintained by 
 the board for receiving notice of proposed large electric 
 generating power plants and high voltage transmission lines.
Subd. 2c.    Environmental review.  The board shall 
 prepare an environmental impact statement on each proposed large 
 electric generating plant or high voltage transmission line for 
 which a complete application has been submitted.  For any 
 project that has obtained a certificate of need from the public 
 utilities commission, the board shall not consider whether or 
 not the project is needed.  No other state environmental review 
 documents shall be required.  The board shall study and evaluate 
 any site or route proposed by an applicant and any other site or 
 route the board deems necessary that was proposed in a manner 
 consistent with rules adopted by the board concerning the form, 
 content, and timeliness of proposals for alternate sites or 
 routes.  
Subd. 2d.    Public hearing.  The board shall hold a 
 public hearing on an application for a site permit for a large 
 electric power generating plant or a route permit for a high 
 voltage transmission line….
Subd. 4.    Considerations in designating sites and 
 routes.  The board's site and route permit determinations must 
 be guided by the state's goals to conserve resources, minimize 
 environmental impacts, minimize human settlement and other land 
 use conflicts, and ensure the state's electric energy security 
 through efficient, cost-effective power supply and electric 
 transmission infrastructure.  To facilitate the study, research, 
 evaluation and designation of sites and routes, the board shall 
 be guided by, but not limited to, the following considerations: 
(1) Evaluation of research and investigations relating to....
electric and magnetic fields resulting from such facilities 
on public health and welfare
(7) Evaluation of alternatives to the applicant's proposed 
site or route proposed pursuant to subdivisions 1 and 2; 
(8) Evaluation of potential routes that would use or 
parallel existing railroad and highway rights-of-way; 
(10) Evaluation of the future needs for additional high 
 voltage transmission lines in the same general area as any 
 proposed route, and the advisability of ordering the 
 construction of structures capable of expansion in transmission 
 capacity through multiple circuiting or design modifications;
Subd. 7.    Timing.  The board shall make a final 
 decision on an application within 60 days after receipt of the 
 report of the administrative law judge.
Subd. 8.    Final decision.  (a) No site permit shall be 
 issued in violation of the site selection standards and criteria 
 established in this section and in rules adopted by the board. 
(b) No route permit shall be issued in violation of the 
 route selection standards and criteria established in this 
 section and in rules adopted by the board. 
 
116C.575 Alternative review of applications.
Subdivision 1.    Alternative review.  An applicant who 
 seeks a site permit or route permit for one of the projects 
 identified in this section shall have the option of following 
 the procedures in this section rather than the procedures in 
 section 116C.57.  The applicant shall notify the chair at the 
 time the application is submitted which procedure the applicant 
 chooses to follow. 
Subd. 2.    Applicable projects.  The requirements and 
 procedures in this section apply to the following projects:  
(3) high voltage transmission lines of between 100 and 200 
 kilovolts; 
Subd. 3.    Application.  The applicant for a site or 
 route permit for any of the projects listed in subdivision 2 who 
 chooses to follow these procedures shall submit information as 
 the board may require, but the applicant shall not be required 
 to propose a second site or route for the project.  The 
 applicant shall identify in the application any other sites or 
 routes that were rejected by the applicant and the board may 
 identify additional sites or routes to consider during the 
 processing of the application.
Subd. 5.    Environmental review.  For the projects 
 identified in subdivision 2 and following these procedures, the 
 board shall prepare an environmental assessment.  The 
 environmental assessment shall contain information on the human 
 and environmental impacts of the proposed project and other 
 sites or routes identified by the board and shall address 
 mitigating measures for all of the sites or routes considered.  
 The environmental assessment shall be the only state 
 environmental review document required to be prepared on the 
 project.  
Subd. 6.    Public hearing.  The board shall hold a 
 public hearing in the area where the facility is proposed to be 
 located.
Subd. 7.    Timing.  The board shall make a final 
 decision on an application within 60 days after completion of 
 the public hearing. 
Subd. 8.    Considerations.  The considerations in 
 section 116C.57, subdivision 4, shall apply to any projects 
 subject to this section.
Subd. 9.    Final decision.  (a) No site permit shall be 
 issued in violation of the site selection standards and criteria 
 established in this section and in rules adopted by the board. 
 
116C.576 Local review of applications.
Subdivision 1.    Local review.  (a) Notwithstanding the 
 requirements of sections 116C.57 and 116C.575, an applicant who 
 seeks a site or route permit for one of the projects identified 
 in this section shall have the option of applying to those local 
 units of government that have jurisdiction over the site or 
 route for approval to build the project.
(b) A local unit of government with jurisdiction over a 
 project identified in this section to whom an applicant has 
 applied for approval to build the project may request the board 
 to assume jurisdiction and make a decision on a site or route 
 permit under the applicable provisions of sections 116C.52 to 
 116C.69.  A local unit of government must file the request with 
 the board within 60 days after an application for the project 
 has been filed with any one local unit of government. 
 
116C.64 Failure to act. 
 If the board fails to act within the times specified in 
 section 116C.57, the applicant or any affected person may seek 
 an order of the district court requiring the board to designate 
 or refuse to designate a site or route. 


 

Excerpts from Minnesota Chapter 216B Regarding PUC Oversight
(Sections of particular interest are shown in italics)
 
216B.2421 Definition of large energy facility. 
 
    Subdivision 1.    Applicability.  The definition in this 
 section applies to this section and sections 216B.2422 and 
 216B.243. 
 
    Subd. 2.    Large energy facility.  "Large energy 
 facility" means: 
 
    (3) any high-voltage transmission line with a capacity of 
 100 kilovolts or more with more than ten miles of its length in 
 Minnesota or that crosses a state line; 
 
(Note there are only two subdivisions in this section.  There is no Subdivision 6 cited by Judge Stacey)
 
216B.2425 State transmission plan. 
 
    Subdivision 1.    List.  The commission shall maintain a 
 list of certified high-voltage transmission line projects. 
 
    Subd. 2.    List development.  (a) By November 1 of each 
 odd-numbered year, each public utility, municipal utility, and 
 cooperative electric association, or the generation and 
 transmission organization that serves each utility or 
 association, that owns or operates electric transmission lines 
 in Minnesota shall jointly or individually submit a transmission 
 projects report to the commission.  The report must: 
 
    (1) list specific present and reasonably foreseeable future 
 inadequacies in the transmission system in Minnesota; 
 
    (2) identify alternative means of addressing each 
 inadequacy listed; 
 
    (3) identify general economic, environmental, and social 
 issues associated with each alternative; and 
 
    (4) provide a summary of public input the utilities and 
 associations have gathered related to the list of inadequacies 
 and the role of local government officials and other interested 
 persons in assisting to develop the list and analyze 
 alternatives. 
 
    (b) To meet the requirements of this subdivision, entities 
 may rely on available information and analysis developed by a 
 regional transmission organization or any subgroup of a regional 
 transmission organization and may develop and include additional 
 information as necessary.  
 
    Subd. 3.    Commission approval.  By June 1 of each 
 even-numbered year, the commission shall adopt a state 
 transmission project list and shall certify, certify as 
 modified, or deny certification of the projects proposed under 
 subdivision 2.  The commission may only certify a project that 
 is a high-voltage transmission line as defined in section 
 216B.2421, subdivision 2, that the commission finds is: 
 
    (1) necessary to maintain or enhance the reliability of 
 electric service to Minnesota consumers; 
 
    (2) needed, applying the criteria in section 216B.243, 
 subdivision 3; and 
 
    (3) in the public interest, taking into account electric 
 energy system needs and economic, environmental, and social 
 interests affected by the project. 
 
    Subd. 4.    List; effect.  Certification of a project as 
 a priority electric transmission project satisfies section 
 216B.243.  A certified project on which construction has not 
 begun more than six years after being placed on the list, must 
 be reapproved by the commission. 
 
    Subd. 5.    Transmission inventory.  The department of 
 commerce shall create, maintain, and update annually an 
 inventory of transmission lines in the state.  
 
    Subd. 6.    Exclusion.  This section does not apply to 
 any transmission line proposal that has been approved by, or was 
 pending before, a local unit of government, the environmental 
 quality board, or the public utilities commission on August 1, 
 2001.  
 
216B.243 Certificate of need for large energy facility. 
 
    Subdivision 1.    Assessment of need criteria.  The 
 commission shall, pursuant to chapter 14 and sections 216C.05 to 
 216C.30 and this section, adopt assessment of need criteria to 
 be used in the determination of need for large energy facilities 
 pursuant to this section. 
 
    Subd. 2.    Certificate required.  No large energy 
 facility shall be sited or constructed in Minnesota without the 
 issuance of a certificate of need by the commission pursuant to 
 sections 216C.05 to 216C.30 and this section and consistent with 
 the criteria for assessment of need. 
 
    Subd. 3.    Showing required for construction.  No 
 proposed large energy facility shall be certified for 
 construction unless the applicant can show that demand for 
 electricity cannot be met more cost effectively through energy 
 conservation and load-management measures and unless the 
 applicant has otherwise justified its need.  In assessing need, 
 the commission shall evaluate: 
 
    (1) the accuracy of the long-range energy demand forecasts 
 on which the necessity for the facility is based; 
 
    (2) the effect of existing or possible energy conservation 
 programs under sections 216C.05 to 216C.30 and this section or 
 other federal or state legislation on long-term energy demand; 
 
    (3) the relationship of the proposed facility to overall 
 state energy needs, as described in the most recent state energy 
 policy and conservation report prepared under section 216C.18; 
 
    (4) promotional activities that may have given rise to the 
 demand for this facility; 
 
    (5) benefits of this facility, including its uses to 
 protect or enhance environmental quality, and to increase 
 reliability of energy supply in Minnesota and the region; 
 
    (6) possible alternatives for satisfying the energy demand 
 or transmission needs including but not limited to potential for 
 increased efficiency and upgrading of existing energy generation 
 and transmission facilities, load-management programs, and 
 distributed generation; 
 
    (7) the policies, rules, and regulations of other state and 
 federal agencies and local governments; and 
 
    (8) any feasible combination of energy conservation 
 improvements, required under section 216B.241, that can (i) 
 replace part or all of the energy to be provided by the proposed 
 facility, and (ii) compete with it economically. 
 
    Subd. 5.    Approval, denial, or modification.  Within 
 six months of the submission of an application, the commission 
 shall approve or deny a certificate of need for the facility.  
 Approval or denial of the certificate shall be accompanied by a 
 statement of the reasons for the decision.  Issuance of the 
 certificate may be made contingent upon modifications required 
 by the commission. 
 
    Subd. 6.    Application fees; rules.  [omitted]
 
    Subd. 7.    Participation by other agency or political 
 subdivision.  [omitted]
 
    Subd. 8.    Exemptions.  This section does not apply to: 
 
    (1) cogeneration or small power production facilities as 
 defined in the Federal Power Act, United States Code, title 16, 
 section 796, paragraph (17), subparagraph (A), and paragraph 
 (18), subparagraph (A), and having a combined capacity at a 
 single site of less than 80,000 kilowatts or to plants or 
 facilities for the production of ethanol or fuel alcohol nor in 
 any case where the commission shall determine after being 
 advised by the attorney general that its application has been 
 preempted by federal law; 
 
    (2) a high-voltage transmission line proposed primarily to 
 distribute electricity to serve the demand of a single customer 
 at a single location, unless the applicant opts to request that 
 the commission determine need under this section or section 
 216B.2425; 
 
    (3) the upgrade to a higher voltage of an existing 
 transmission line that serves the demand of a single customer 
 that primarily uses existing rights-of-way, unless the applicant 
 opts to request that the commission determine need under this 
 section or section 216B.2425; 
 
    (4) a high-voltage transmission line of one mile or less 
 required to connect a new or upgraded substation to an existing, 
 new, or upgraded high-voltage transmission line; 
 
    (5) conversion of the fuel source of an existing electric 
 generating plant to using natural gas; or 
 
    (6) modification of an existing electric generating plant 
 to increase efficiency, as long as the capacity of the plant is 
 not increased more than ten percent or more than 100 megawatts, 
 whichever is greater.